File #: 16-702    Name: Master Plan Update
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 7/19/2016 Final action: 7/19/2016
Title: Consider/Discuss/Act on a Resolution Naming the Texas Department of Transportation as the City's Agent to Administer an Airport Master Plan Update and Authorizes the Interim City Manager or City Manager to Execute All Documents and Agreements with the State of Texas for the Airport Master Plan Update Project
Attachments: 1. Resolution

Title

Consider/Discuss/Act on a Resolution Naming the Texas Department of Transportation as the City’s Agent to Administer an Airport Master Plan Update and Authorizes the Interim City Manager or City Manager to Execute All Documents and Agreements with the State of Texas for the Airport Master Plan Update Project

 

Summary

 

COUNCIL GOAL:                     Maximize the Development Potential of the McKinney National Airport

 

MEETING DATE:                     July 19, 2016

 

DEPARTMENT:                      Airport

 

CONTACT:                       Kenneth Wiegand, Airport Director

 

 

RECOMMENDED CITY COUNCIL ACTION:                     

                     Approval of Resolution

 

ITEM SUMMARY: 

                     This Resolution names the Texas Department of Transportation (TxDOT) as the City’s agent to administer an Airport Master Plan Update (MPU) project.

                     Ensures TxDOT that the City of McKinney supports the project’s implementation and is prepared to meet its 10% cost share of the project.

                     Authorizes the Interim City Manager or City Manager to execute all documents and agreements with the State of Texas for the MPU that will earn the City a 90% federal funding grant for the cost of the project.

 

BACKGROUND INFORMATION: 

                     The last MPU was conducted in 2003 and 2004 and approved February 2006.

                     An Airport Layout Plan (ALP) Update was conducted in 2011-12 as a result of constructing a new control tower and runway. 

                     This MPU was requested and approved as a project by TxDOT in response to significant events having an impact on the operations of McKinney National Airport since the 2012 ALP Update.

                     Those events include acquisition of the FBO and its facilities, creation of   McKinney Air Center, increased aircraft operations, increased demand for hangars, aircraft and auto parking, an expanded GA passenger terminal and relocation of the US Customs office.

 

FINANCIAL SUMMARY:

                     The City’s 10% share, approximately $33,333 is available in the FY16 Airport Operating Fund budget.

 

                     The grant and match will be included in the FY2017 - 2021 Capital Improvement Program as Project AI1648.

 

Project

Total Amount

Federal Share

City Share

Master Plan Update

$333,333

$300,000

$33,333

 

 

BOARD OR COMMISSION RECOMMENDATION:                     N/A