File #: 16-837    Name: Budget Amendment for Fire Station #9
Type: Ordinance Status: Approved
In control: City Council Regular Meeting
On agenda: 8/16/2016 Final action: 8/16/2016
Title: Consider/Discuss/Act on an Ordinance Amending the 2016 - 2020 Capital Improvements Projects Budget by Transferring Funds from the Facilities Construction Fund Balance to Project FI3244 for the Construction of McKinney Fire Station #9 Located at 4900 Summit View Drive, McKinney, Texas
Attachments: 1. Ordinance

Title

Consider/Discuss/Act on an Ordinance Amending the 2016 - 2020 Capital Improvements Projects Budget by Transferring Funds from the Facilities Construction Fund Balance to Project FI3244 for the Construction of McKinney Fire Station #9 Located at 4900 Summit View Drive, McKinney, Texas

 

Summary

 

COUNCIL GOAL:                     Safe and Secure Community

 

MEETING DATE:                     August 16, 2016

 

DEPARTMENT:                      Fire Department

                     Public Works Department, Facilities Construction Division

 

CONTACT:                       Danny Kistner, Fire Chief

                     Patricia L. Jackson, PE, Facilities Construction Manager

 

 

RECOMMENDED CITY COUNCIL ACTION:                     

                     Approval of the Ordinance.

 

ITEM SUMMARY: 

                     This Ordinance amends expenditures in the 2016 - 2020 Capital Improvements Projects Budget by transferring $1,085,505 from the Facilities Construction Fund balance to Project FI3244 for the construction of McKinney Fire Station #9 located at 4900 Summit View Drive, McKinney, Texas.

 

BACKGROUND INFORMATION: 

                     On April 5, 2016 a professional services contract was authorized to provide Construction Manager at Risk (CMAR) services related to the preconstruction phase of McKinney Fire Station #9 located at 4900 Summit View Drive, McKinney, Texas, 75071 for an amount not to exceed $12,500 based upon a proposal for $10,000 in fees for pre-construction services and fees of 3.25% for construction services.

                     Lee Lewis Construction, Inc. publicly bid the project, has compiled the bids and submitted a final Guaranteed Maximum Price for approval.

                     With this approval, Lee Lewis Construction, Inc. will be notified to begin construction with completion scheduled for October 2017.

                     This Ordinance amends the 2016 - 2020 Capital Improvements Projects budget to fund the project.

 

FINANCIAL SUMMARY: 

                     The McKinney Fire Station #9 Project (FI3244) was funded within the FY15-16 Capital Improvements Program with general obligation bonds.

                     With approval of this budget amendment, the total budget for project FI3244 will be $8,556,505.

                     There is a companion agenda item for a Construction Manager at Risk (CMAR) contract amendment related to this project also included in this Council session.

 

BOARD OR COMMISSION RECOMMENDATION:

                     N/A