Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Birkhoff, Hendricks & Carter, LLP (BHC) for Professional Engineering Design Services for the McKinney Substandard Utility Replacement and Street Rehabilitation Umbrella Projects South of Virginia and Any Necessary Supplemental Agreements
Summary
COUNCIL GOAL: Direction for Strategic and Economic Growth
MEETING DATE: April 4, 2017
DEPARTMENT: Development Services / Engineering
CONTACT: Gary Graham, PE, PTOE CIP and Transportation Engineering Manager
Nick Ataie, PE, CIP Project Manager
RECOMMENDED CITY COUNCIL ACTION:
* Approval of Resolution.
ITEM SUMMARY:
* This Resolution authorizes a contract with Birkhoff, Hendricks & Carter, LLP (BHC) to provide consulting engineering services for the design of the McKinney Substandard Utility Replacement and Street Rehabilitation Umbrella Projects South of Virginia for an amount not to exceed $327,000.
BACKGROUND INFORMATION:
* FY 17 funding for various street reconstruction for work has been previously identified and programmed under the Street Reconstruction Umbrella (ST1622).
* FY 17 funding for various substandard mains (water and wastewater) has been previously identified and programmed under the Substandard Water Mains (WA4336) and the Substandard Wastewater Mains (WW4350).
* Based on available funding for street reconstruction and substandard mains, staff has identified and allocated funding use for the design of street rehabilitation, water main replacements, and/or sewer main replacements throughout the City based on condition assessment and need.
* Staff has recommended geographical grouping of these projects (which includes construction of street rehabilitations with replacement of substandard mains) in order to minimize disruption to traffic and infrastructure in areas where there is an overlap with proposed construction activities.
* The boundary for this project group is generally defined as South of ...
Click here for full text