File #: 18-422    Name: Structure Tone Amendment
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 5/15/2018 Final action: 5/15/2018
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract Amendment to the Construction Manager at Risk (CMAR) Services Contract with Structure Tone Southwest, LLC of Dallas for Services Related to the Construction of the McKinney National Airport Hangar Renovation Project
Attachments: 1. Resolution

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract Amendment to the Construction Manager at Risk (CMAR) Services Contract with Structure Tone Southwest, LLC of Dallas for Services Related to the Construction of the McKinney National Airport Hangar Renovation Project

 

 

Summary

 

COUNCIL GOAL:                     Maximize Development Potential of the McKinney National Airport

 

MEETING DATE:                     May 15, 2018

 

DEPARTMENT:                      Airport

 

CONTACT:                       Kenneth Carley, A.A.E., Airport Director

 

 

RECOMMENDED CITY COUNCIL ACTION:                     

                     Approval of the Resolution.

 

ITEM SUMMARY: 

                     This Resolution authorizes an increase in the amount of $292,042.99 to the Guaranteed Maximum Price (GMP) contract of $4,329,523.04 for change requests by both the City and Tenant.

                     New GMP contract amount totals $4,621,566.03.

 

BACKGROUND INFORMATION: 

                     Toyota Motors North America (tenant) requested to expand the existing hangar at McKinney National Airport.  Tenant has signed a new 10 year lease with the City of McKinney.

                     GMP in the amount of $4,262,834 was authorized by Council on June 20, 2017 for CMAR services for the construction and expansion of the hangar.

                     Increase to GMP by $66,689.04 was authorized by Council on April 3, 2018 for Change Requests No. 1 through No. 3.

                     Change Request No. 4 is being requested to meet the needs of both the City and Tennant and is comprised of the following:

 

Description

Cost

Change Request No.

Requested By:

Additional cost for revised span guard

$1,166.92

CR 019

Tenant

Additional line for pre-action system at canopy

$4,216.91

CR 020

Design Change to avoid Water Meter

Form & Pour Gate Controller Pad on North Side

$315.95

CR 022

Tenant

GCO 19 - Move Outlets in Pilots Room

$2,311.72

CR 023

Tenant

GCO 20 - Add Power @ refrigerator in pantry

$1,105.84

CR 024

Tenant

GCO 21 - Directional Covers for Tarmac lights

$737.22

CR 025

Tenant

Fire Hydrant Relocation 2' south and east

$1,800.93

CR 026

City Fire Marshall

TCO 20 - Saw cut for security access conduit @ gate

$526.59

CR 027

Tenant

Weld Plates and angles @ mezanine & columns

$5,185.83

CR 028

Tenant

Replace "Yellow" FRP 75 Pieces

$10,742.39

CR 029

Tenant

GCO 18 - Inverter for lobby lights

$3,317.51

CR 030

Tenant

Epoxy first floor of 174

$32,806.41

CR 031

Tenant

Upgrade Existing Fire Alarm Panel per Fire Marshalls Requirements

$51,057.92

CR 032

City Fire Marshall

Reseal Hangar Floor

$145,386.60

CR 033

Tenant

Sod per cities direction

$3,299.98

CR 034

City

Hydromulch per City Direction outside the landscape plans

$4,422.47

CR 035

City

Change of Landscaping at Plants per Tenant

$8,444.00

CR 036

Tenant

Change of Parking Canopy Column Decorative Wraps to Cast Stone

$15,197.80

CR 037

Tenant

 CHANGE REQUEST TOTAL

$292,042.99

 

 

 

FINANCIAL SUMMARY: 

                     Funding for this increase is currently available in Project AI1705.

 

BOARD OR COMMISSION RECOMMENDATION:

                     N/A