File #: 18-500    Name: PB George Webb Construction Contract
Type: Agenda Item Status: Approved
In control: Parks, Recreation, and Open Space Advisory Board
On agenda: 6/14/2018 Final action: 6/14/2018
Title: Consider/Discuss/Act on a Recommendation to City Council for a Resolution Authorizing the City Manager to Execute a Contract with AUI Partners, LLC of Fort Worth, Texas, for the Construction of the George Webb Park Project Located at 10450 Millbend Drive
Attachments: 1. Bid Tabulation, 2. Landscape and Site Layout
Title
Consider/Discuss/Act on a Recommendation to City Council for a Resolution Authorizing the City Manager to Execute a Contract with AUI Partners, LLC of Fort Worth, Texas, for the Construction of the George Webb Park Project Located at 10450 Millbend Drive

Summary

COUNCIL GOAL: Enhance the Quality of Life in McKinney
Direction of Strategic Growth

MEETING DATE: June 14, 2018

DEPARTMENT: Parks and Recreation

CONTACT: Michael Kowski, Director of Parks and Recreation


RECOMMENDED CITY COUNCIL ACTION:
* Approve the recommendation to City Council.

ITEM SUMMARY:
* George Webb Park is an 11 acre neighborhood park that will include a play structure, swings, musical stations, pavilions, a basketball court, trails, and also an interactive water pump that will be set as a part of a dry river bed feature.
* City staff worked with Studio Outside, LLC. a landscape architecture firm, on preparing the construction plans and specifications as needed for project bidding.

* Staff recommends awarding the construction bid to AUI Partners, LLC. in an amount of $2,160,000 and not to exceed $2,375,000 (includes construction contingency).

BACKGROUND INFORMATION:
* A total of 6 bids were submitted and accepted on May 31, 2018.

* AUI Partners, LLC submitted the lowest bid for the construction.

* If approved, construction should begin in July of 2018 with a 240 day (8 month) contract schedule.

FINANCIAL SUMMARY:
* The George Webb Park Project (PK3224) is a FY17-18 Capital Improvements Program funded by MCDC funds and Parkland Dedication Funds Zone 3.

* The original project cost was estimated at $2,425,000. The actual project costs are $2,650,000 which includes all design and development costs and provides for a project contingency.

* The project was bid with 5 possible deduct alternates. The $2,650,000 allows for of the construction of the total base bid without taking any deduct alternates.

o Deduct Alt 1 - 15'x17' Shade Pavilion near Millbend Ro...

Click here for full text