Title

Consider/Discuss/Act on a Resolution Authorizing an Interlocal Agreement with the North Central Texas Council of Governments for the Purchase and Installation of Advance Warning Stations for High Water Crossings; funded through the Texas Water Development Board

 

Summary

 

COUNCIL GOAL:                     Safe and Secure Community

 

MEETING DATE:                     February 5, 2019

 

DEPARTMENT:                      Fire Department - Emergency Management

 

CONTACT:                       Karen Adkins, Emergency Manager
                     Randall Gurney, Assistant EM Coordinator

 

 

RECOMMENDED CITY COUNCIL ACTION:                     

•    Approve the attached Resolution

 

ITEM SUMMARY: 

•    The project, approved by City Council on August 16, 2016 (AI 16-826), approved the application for and acceptance of a grant for the purchase of Advance Warning Stations for high water crossings.

                     The original project was for the purchase of two (2) early warning stations (4 units).  The revised project is for the purchase of three (3) early warning stations (6 units).

                     The original project cost was approximately $140,000. The revised project cost is $152,765.26

                     The original cost to the City was $70,640.  The revised cost to the City is $77,340

 

BACKGROUND INFORMATION: 

                     The attached Interlocal Agreement defines McKinney’s role as subrecipient of funds for implementation of the provisions of the NCTCOG Early Flood Warning Detection Project (“Project”) funded by the Texas Water Development Board (TWDB) planning grant to develop an early flood warning system.

 


 

 

FINANCIAL SUMMARY: 

                     

Budget Category

McKinney "In-Kind" Match

McKinney Cash Match

Reimbursement to McKinney

Total

McKinney Labor

$9,060.00

 

 

$9,060.00

Materials & Maintenance

$21,300.00

 

 

$21,300.00

Equipment

$1,980.00

$45,000.00

$49,175.26

$96,155.26

Software (5 yr subscription)

 

 

$26,250.00

$26,250.00

TOTAL

$32,340.00

$45,000.00

$75,425.26

$152,765.26

 

BOARD OR COMMISSION RECOMMENDATION: