File #: 19-0138    Name: Virginia 5&6 Design Contract
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 2/19/2019 Final action: 2/19/2019
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Jacobs Engineering Inc. for Professional Engineering Design Services for the ST1839 - Virginia Pkwy Lanes 5 & 6 from Custer Rd to Virginia Parklands Blvd Project and Any Necessary Supplemental Agreements
Attachments: 1. Resolution, 2. Project Location Map

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Jacobs Engineering Inc. for Professional Engineering Design Services for the ST1839 - Virginia Pkwy Lanes 5 & 6 from Custer Rd to Virginia Parklands Blvd Project and Any Necessary Supplemental Agreements

 

Summary

 

COUNCIL GOAL:                     Operational Excellence

                     (2B: Balance available resources to accommodate the growth and maintenance needs of the city)

 

MEETING DATE:                     February 19, 2019

 

DEPARTMENT:                        Development Services / Engineering                     

 

CONTACT:                       Nick Ataie, PE, CIP Engineering Manager

                     Jason Horn, PE, CIP Project Manager

 

RECOMMENDED CITY COUNCIL ACTION:                     

                     Approval of Resolution.

 

ITEM SUMMARY: 

                     This Resolution authorizes the City Manager to execute a contract in the amount of $281,050, as well as all required supplemental agreements thereto, with Jacobs Engineering, Inc. for professional consulting engineering services for the Virginia Pkwy Lanes 5 & 6 from Custer Rd to Virginia Parklands Blvd Project (ST1839), for a total aggregate contract amount, inclusive of any supplemental agreements, not to exceed $310,000.

 

BACKGROUND INFORMATION: 

                     Virginia Parkway is currently a four lane divided arterial from Custer Rd to Virginia Parklands Blvd.

                     Virginia Pkwy is currently identified as a six lane divided major arterial in the adopted Master Thoroughfare Plan.

                     This project will include the widening of Virginia Parkway (within the existing median) from four lanes to six lanes from west of Custer Rd to Virginia Parklands Blvd, a distance of approximately 5,300 feet.  It will also include intersection capacity improvements at the intersection of Virginia Parkway and Custer Road (EB/WB dual left-turns and EB/WB right-turn lanes).

                     Existing median trees and landscaping which are impacted by widening will be mitigated and the project will include relocation, replacement, and/or installation of new landscaping.

                     Jacobs Engineering Inc. submitted a response to RFQ 18-45 for On-call Roadway Design Services.  They were one of twelve firms shortlisted by City Council on October 8, 2018. 

                     Jacobs Engineering Inc. submitted a proposal for this project in the amount of $281,050. Their scope includes the following elements:

o                     Basic Services (Design Services & Bid Phase Services)

o                     Special Services (Field Topographic Survey, Subsurface Utility Exploration, Franchise Utility Coordination, Right-of-Way and Easement Documentation, Environmental Investigations, and Construction Administration Services)

                     The preliminary opinion of probable construction cost (OPCC) is $1,810,642.40.

                     The fee for basic services is $185,526.18 (10.2% of the OPCC) and the fee for special services is $95,523.82 (5.3% of the OPCC).

                     Design of this project is anticipated to take 6 months to complete.  Construction is anticipated to begin as early as December 2019 (contingent on availability of construction funding) and to be completed by June 2020

 

FINANCIAL SUMMARY: 

                     The Resolution authorizes a contract with Jacobs Engineering Inc. for an amount not to exceed $310,000. 

                     Funds are available in the Capital Improvements Program Project ST1839.

                     With the approval of this item, $1,490,000 will remain in ST1839.

 