File #: 19-0197    Name: LI1609 - JJGLE&R - Pogue GMP
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 3/5/2019 Final action: 3/5/2019
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract Amendment to the Construction Manager at Risk (CMAR) Services Contract with Pogue Construction Company, LP of McKinney, Texas for a Guaranteed Maximum Price (GMP) Related to the John and Judy Gay Library Expansion & Renovation (JJGLE&R) Located at 6861 W. Eldorado Parkway, McKinney, Texas 75070
Attachments: 1. Resolution, 2. GMP Proposal

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract Amendment to the Construction Manager at Risk (CMAR) Services Contract with Pogue Construction Company, LP of McKinney, Texas for a Guaranteed Maximum Price (GMP) Related to the John and Judy Gay Library Expansion & Renovation (JJGLE&R) Located at 6861 W. Eldorado Parkway, McKinney, Texas 75070

 

SUMMARY

 

COUNCIL GOAL:                     Enhance the Quality of Life in McKinney

                     (5A: Create Affordable Recreational and Cultural Arts

                     Activities for All AgesThroughout the City

 

MEETING DATE:                     March 5, 2019

 

DEPARTMENT:                      Library Services

                     Public Works

 

CONTACT:                       Spencer Smith - Director of Libraries

                     Patricia L. Jackson, PE - Facilities Construction Manager

                     

RECOMMENDED CITY COUNCIL ACTION:                     

                     Approval of the Resolution.

 

ITEM SUMMARY: 

                     This Resolution authorizes the City Manager to execute a contract amendment with Pogue Construction Company, LP for a Guaranteed Maximum Price (GMP) of $8,640,170 to provide Construction Manager at Risk services associated with the John and Judy Gay Library Expansion & Renovation located at 6861 W. Eldorado Parkway, McKinney, Texas 75070.

 

BACKGROUND INFORMATION: 

                     The construction manager at risk for construction to be done at the John and Judy Gay Library Expansion & Renovation was selected through a two-step Request for Qualifications (RFQ) selection process in 2017 with 17-60RFQ where Pogue Construction Company, LP was the selected vendor.

                     Pogue Construction Company, LP submitted a proposal to provide construction services related to the John and Judy Gay Library Expansion & Renovation Project LI1609 for a not to exceed amount of $8,640,170.

                     Pogue Construction Company, LP has successfully completed multiple City of McKinney projects including the original John and Judy Gay Library as well as a variety of civic facility projects for McKinney and other municipalities. 

 

FINANCIAL SUMMARY: 

                     The Resolution authorizes the City Manager to execute a contract amendment with a guaranteed maximum price (GMP) for Construction Manager at Risk (CMAR) services with Pogue Construction Company, LP for an amount not to exceed $8,640,170. This amount includes an owner’s contingency of $160,639 along with the previously agreed upon 3.25% CMAR fee.

                     The not to exceed amount of $8,640,170 will be split between two projects. ($1,206,825 for PK1806, Gabe Nesbitt Community Park Improvements Project, and $7,433,345 for LI1609, John and Judy Gay Library Expansion and Renovation Project).

                     The John and Judy Gay Library Expansion and Renovation (LI1609) was funded within the FY16-17 Capital Improvements Program by general obligation funds and funds approved in the 2015 bond election.

                     In PK1806, there is a remaining balance of $5,129,745 of which, $1,250,000 is dedicated to the John and Judy Gay Library Expansion and Renovation Project (JJGLE&R). The amount expended for design services was $43,175 leaving $1,206,825 dedicated to be used for construction of the associated park improvements on the JJGLE&R. 

                     The balance remaining in PK1806 upon approval of this item will be $3,922,920.

                     In LI1609, there is a budget of $9,500,000 with a remaining balance of $8,544,584. With approval of this item, and the companion agenda item, the total project balance remaining in Project LI1609 will be $1,056,011.

 

BOARD OR COMMISSION RECOMMENDATION:

                     This item was reviewed by the Library Advisory Board on February 21, 2019.