File #: 20-0255    Name: Harry McKillop Illumination Design
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 3/17/2020 Final action: 3/17/2020
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Maldonado-Burkett, LLP. to Provide Consulting Engineering Services for the TR2021 - Harry McKillop Boulevard Illumination and Authorizing Any Supplemental Agreements
Attachments: 1. Resolution, 2. Location Map

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Maldonado-Burkett, LLP. to Provide Consulting Engineering Services for the TR2021 - Harry McKillop Boulevard Illumination and Authorizing Any Supplemental Agreements

 

Summary

 

COUNCIL GOAL:                     Operational Excellence

(2B: Balance available resources to accommodate the growth and maintenance needs of the city)

 

MEETING DATE:                     March 17, 2020

 

DEPARTMENT:                      Development Services/Engineering

 

CONTACT:                       Thuan Huynh, PE, Engineering Transportation Manager

                     Gary Graham, PE, PTOE, Director of Engineering

 

 

RECOMMENDED CITY COUNCIL ACTION:                     

                     Approval of Resolution.

 

ITEM SUMMARY: 

                     This Resolution authorizes the City Manager to execute a contract in the amount of $116,975, as well as all required supplemental agreements thereto, with Maldonado-Burkett, LLP. for professional consulting engineering services for the design of continuous roadway illumination on Harry McKillop Boulevard from State Highway 5 (McDonald Street) to Airport Drive, for a total aggregate contract amount, inclusive of any supplemental agreements, not to exceed $135,000.

 

BACKGROUND INFORMATION: 

                     Harry McKillop Boulevard was constructed in 2018 by TxDOT and the continuous roadway illumination was not included with the project.  Harry McKillop Boulevard has been identified and recommended for installation of continuous roadway illumination by City of McKinney Engineering Department.

                     Maldonado-Burkett, LLP. submitted a response to 2018-02RFQ for traffic engineering services.  They were one of three firms shortlisted in the traffic engineering studies category by City Council on January 16, 2018.

                     Construction of this project is estimated to cost a total of approximately $705,000.

                     Maldonado-Burkett, LLP. submitted a proposal for this project in the amount of $116,975 (16.6% of the overall estimated construction cost) to perform the engineering services. Additional services, if needed, will be provided on an hourly basis, as needed during the design and construction.

                     Upon approval of the engineering services contract, Maldonado-Burkett, LLP. will perform the design and prepare the construction documents for the project.

FINANCIAL SUMMARY: 

                     This Resolution authorizes a contract with Maldonado-Burkett, LLP. for an amount not to exceed $135,000.

                     Funds are available in the Capital Improvements Program TR2021 ($135,000).

 

                     With the approval of this item, $705,000 will remain in TR2021.

 

BOARD OR COMMISSION RECOMMENDATION:

                     N/A