File #: 20-0324    Name: Runway 18-36 Joint Rehabilitation Project Funding
Type: Ordinance Status: Approved
In control: City Council Regular Meeting
On agenda: 4/21/2020 Final action: 4/21/2020
Title: Consider/Discuss/Act on an Ordinance Amending the Fiscal Year 2019-2020 Annual Budget and the 2020-2024 Capital Improvements Program to Provide Funds for the Runway 18-36 Joint Rehabilitation Project (AI2064-Airfield Pavement Rehabilitation) at the McKinney National Airport; and Providing an Effective Date
Attachments: 1. Ordinance
Title
Consider/Discuss/Act on an Ordinance Amending the Fiscal Year 2019-2020 Annual Budget and the 2020-2024 Capital Improvements Program to Provide Funds for the Runway 18-36 Joint Rehabilitation Project (AI2064-Airfield Pavement Rehabilitation) at the McKinney National Airport; and Providing an Effective Date

Summary

COUNCIL GOAL: Maximize the Development Potential of the McKinney National Airport
3B: Identify and implement land use regulations and policies with preserve and expand long-term operational excellence.

MEETING DATE: April 21, 2020

DEPARTMENT: Airport

CONTACT: Ken Carley, Airport Director


RECOMMENDED CITY COUNCIL ACTION:
* Approve Ordinance

ITEM SUMMARY:
* This Ordinance amends the Fiscal Year 2019-2020 Annual Budget and the 2020-2024 Capital Improvements Program by appropriating $198,000 in the Airport Construction Fund for Project AI2064 Airfield Pavement Rehab; and transferring $242,400 from AI1816 Customs Building Project to AI2064 Airfield Pavement Rehab Project.

BACKGROUND INFORMATION:
* Total Project costs are estimated to be $432,400.

* TxDOT has programmed $198,000 in its Aviation Capital Improvement Program to reimburse a portion of the Airfield Pavement Rehabilitation costs, however, the project is required to be completed this fiscal year to be eligible.

* CIP Project AI1816 (CUSTOMS BLDG AT AIRPORT) currently has $2,569,449 programmed, with an estimated total cost of $5,500,000. Design and work have not begun for this project while the remaining funding is considered. Staff is recommending to transfer $234,400 from this project to meet TXDOT's reimbursement eligibility deadline on the Airfield Pavement Rehab project.

* The City will be responsible for administering the project and will seek reimbursement for eligible construction costs, not to exceed $198,000, upon project completion.


FINANCIAL SUMMARY:
* The financial summary attached to the ordinance details the additional appropriation of $198,000 in the...

Click here for full text