File #: 20-0651    Name: Design Services for Project ST1839
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 8/4/2020 Final action: 8/4/2020
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Supplemental Agreement with Jacobs Engineering Inc. for Professional Engineering Design Services for the Virginia Pkwy Lanes 5 & 6 from Custer Rd to Virginia Parklands Blvd (ST1839)
Attachments: 1. Resolution, 2. Project Location Map, 3. Right Turn Lane Exhibit
Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Supplemental Agreement with Jacobs Engineering Inc. for Professional Engineering Design Services for the Virginia Pkwy Lanes 5 & 6 from Custer Rd to Virginia Parklands Blvd (ST1839)

Summary

COUNCIL GOAL: Operational Excellence
(2B: Balance available resources to accommodate the growth and maintenance needs of the city)

MEETING DATE: August 4, 2020

DEPARTMENT: Development Services / Engineering

CONTACT: Nick Ataie, P.E., Engineering CIP Manager
Jason Horn, P.E., Civil Engineer


RECOMMENDED CITY COUNCIL ACTION:
* Approval of Resolution.

ITEM SUMMARY:
* This Resolution authorizes a supplemental agreement with Jacobs Engineering Inc. to provide additional professional engineering services for the design of the Virginia Pkwy Lanes 5 & 6 from Custer Rd to Virginia Parklands Blvd for an increase in the not to exceed fee by $90,000 (from $310,000) for a total aggregate contract amount, inclusive of any additional supplemental agreements, not to exceed $400,000.

BACKGROUND INFORMATION:
* Jacobs Engineering Inc. is currently under contract with the City for design services related to the Virginia Pkwy Lanes 5 & 6 from Custer Rd to Virginia Parklands Blvd.
* The design for the project is currently 90% complete and has been underway since February 2019. Construction of the planned improvements is expected to occur as soon as March 2021.
* As detailed design has progressed, the following additional services have been requested by the Engineering Department which were not originally included in current Jacobs Engineering Inc.'s contract:
o Addition of three new dedicated right turn lanes at Cranberry Ln., Virginia Parklands Blvd., and St. Gabriel Way including survey at each roadway, and modifications to the plans to reflect the changes throughout.
o Intersection grading sheets for Cranberry Ln, Virginia Parklands Blvd, and St. Gabriel Way in order to provide ADA compliant cross ...

Click here for full text