File #: 20-0795    Name: EST Maint. Design Contract - BHC
Type: Resolution Status: Consent Item
In control: City Council Regular Meeting
On agenda: 9/15/2020 Final action:
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract and Authorize Any Supplemental Agreements with Birkhoff, Hendricks & Carter, LLP for Consulting Engineering Services for the Elevated Storage Tank Maintenance Project (WA1851)
Attachments: 1. Resolution, 2. Location Map - Independence, 3. Location Map - Wilmeth
Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract and Authorize Any Supplemental Agreements with Birkhoff, Hendricks & Carter, LLP for Consulting Engineering Services for the Elevated Storage Tank Maintenance Project (WA1851)

Summary

COUNCIL GOAL: Operational Excellence
(2B: Balance available resources to accommodate the growth and maintenance needs of the City)

MEETING DATE: September 15, 2020

DEPARTMENT: Development Services / Engineering

CONTACT: Nick Ataie, PE, Engineering CIP Manager
Paul Tucker, PE, Senior Utility Engineer

RECOMMENDED CITY COUNCIL ACTION:
* Approval of Resolution

ITEM SUMMARY:
* This Resolution authorizes a contract with Birkhoff, Hendricks & Carter, LLP to provide consulting engineering services for the Elevated Storage Tank Maintenance Project (WA1851) for an amount not to exceed $150,000.

BACKGROUND INFORMATION:
* The existing 2.0 Million Gallons (MG) Wilmeth Elevated Storage Tank located at 2890 CR 943 west side of the Erwin Farms subdivision serves the 850-pressure plane of the City's water distribution system.
o The existing Wilmeth Elevated Storage Tank has been identified for repairs and repainting based on the Wilmeth 2.0-MG Elevated Storage Tank Facility Assessment report dated May 11, 2020. The field inspection was performed by Birkhoff, Hendricks & Carter LLP and Axis Construction, LP on April 8, 2020. During this inspection temporary steel patch repairs were made to the interior of the tank to immediately mitigate active leaks.
o A topographic field survey of the Wilmeth Elevated Storage Tank Site will be performed to obtain tank footprint, driveway, fence line, and other surface features. The survey will be used to determine construction access and staging area, ground clearance for the paint shroud that extends from the top of the tank to ground surface, and additional protection for equipment that may be located inside of the paint shroud area.

* The existing 3.0 Mil...

Click here for full text