File #: 21-0669    Name: Advanced Metering Infrastructure (AMI) System
Type: Agenda Item Status: Agenda Ready
In control: City Council Work Session
On agenda: 8/3/2021 Final action:
Title: Presentation on the Advanced Metering Infrastructure (AMI) System
Attachments: 1. Scoring, 2. Presentation
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Presentation on the Advanced Metering Infrastructure (AMI) System

 

Summary

 

COUNCIL GOAL:                     Enhance the Quality of Life in McKinney                                                               

(5E: Develop sustainable quality of life improvements)

(5G: Promote sustainability by creating “green” initiatives.)

 

MEETING DATE:                     August 3, 2021

 

DEPARTMENT:                      Utility Customer Operations

 

CONTACT:                       Mark Holloway, Chief Financial Officer

                     Alexandra Casey, Utility Customer Operations Manager

                     Patrick Hackler, Assistant Manager / Meter Operations

 

 

ITEM SUMMARY: 

                     Award and execute a contract with HPS, LLC doing business as HydroPro Solutions, LLC of Georgetown, Texas in the amount of $11,257,875 for the development and implementation of an Advanced Metering Infrastructure (AMI) System, WA2051.

 

BACKGROUND INFORMATION: 

                     A committee comprised of staff from the Meter Services and Customer Operations departments reviewed and ranked seven (7) proposals. HydroPro Solutions best met our criteria.

                     A proof-of-concept will be conducted for up to six (6) months.  600 homes, located in McKinney’s southwest sector, were identified to test the AMI’s system distance and density capacity.

                     AMI fosters water conservation and advances customer service by providing a mechanism (online portal and mobile app) to identify water use. The data will help staff address the cause of a high bill amount.

                     Customer account transitions will be streamlined to reduce service interruptions and staff field visits.

                     By selecting HydroPro, our in-ground meters will easily interface with the AMI register.  No additional parts are required, a cost savings of over $4 million. 

 

FINANCIAL SUMMARY: 

                     The Advanced Metering System project (WA2051) is budgeted in the FY2021-2025 Capital Improvements Program and includes $7,000,000 of funding from Revenue Bonds and Utility Construction Fund Balance.  $4,000,000 of additional Revenue Bonds and $260,000 of additional Utility Construction Fund Balance will be added to the project as a FY21 end of year adjustment.