Legislation Details

File #: 24-2106    Name: Formal Rejection of Proposals under Solicitation 25-01CSP
Type: Resolution Status: Consent Item
In control: City Council Regular Meeting
On agenda: 10/15/2024 Final action:
Title: Consider/Discuss/Act on a Resolution Authorizing the Formal Rejection of all Proposals under Solicitation 25-01CSP Construction of Chestnut 0.5 MG Elevated Storage Tank Rehabilitation
Attachments: 1. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Consider/Discuss/Act on a Resolution Authorizing the Formal Rejection of all Proposals under Solicitation 25-01CSP Construction of Chestnut 0.5 MG Elevated Storage Tank Rehabilitation

 

 

Summary

 

COUNCIL GOAL:                     Operational Excellence

(2A: Balance available resources to accommodate the growth and maintenance needs of the city)

 

MEETING DATE:                     October 15, 2024

 

DEPARTMENT:                      Engineering

                     Procurement Services

 

CONTACT:                       Paul Tucker, Senior Utility Engineer

                     Blake Sills, CIP Manager

                     Mindy Smith, Assistant Procurement Services Manager

                     

 

RECOMMENDED CITY COUNCIL ACTION:

•                     Approval of Resolution

 

ITEM SUMMARY:

•                     This Resolution authorizes formal rejection of all proposals under 25-01CSP Construction of Chestnut 0.5 MG Elevated Storage Tank Rehabilitation.

 

BACKGROUND INFORMATION:

•                     The City issued a Request for Competitive Sealed Proposals (25-01CSP) for the Construction of Chestnut 0.5 MG Elevated Storage Tank Rehabilitation August 18, 2024.

o                     Advertised in the McKinney Courier Gazette and Celina Record

o                     Posted on McKinney TV

o                     1065 matching eBid supplier notifications which included 49 Historically Underutilized Business (HUB) suppliers.

•                     Out of 1065 supplier notifications, one (1) proposal was received and opened by Procurement Services on September 12, 2024. The following is a summary of the proposal:

 

Bidder

Base Bid

Alternate A

Alternate B

Total Amount Bid

Blastco Texas Inc

$4,758,675.00

$165,600.00

$28,291.00

$4,952,566.00

 

•                     The Engineer’s Opinion of Probable Construction Cost (OPCC) was $2.455 million and the proposal received exceeded the budgeted amount for this project. The Engineering department has elected to reject all proposals and will re-bid this project at a later date.

 

FINANCIAL SUMMARY:

•                     N/A

 

BOARD OR COMMISSION RECOMMENDATION:

•                     N/A