File #: 24-1666    Name: Lift Station Improvements
Type: Resolution Status: Consent Item
In control: City Council Regular Meeting
On agenda: 6/18/2024 Final action:
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with, Freese and Nichols, Inc for Professional Engineering Design Services for the Virginia Hills Lift Station Abandonment (WW2433), Creek Hollow Lift Station Improvements (WW2434), Erwin Farms Lift Station Abandonment (WW2435), and Sloan Creek Lift Station Improvements (WW2436) and Authorizing Any Necessary Supplemental Agreements
Attachments: 1. Resolution, 2. Location Map - WW2433, 3. Location Map - WW2434, 4. Location Map - WW2435, 5. Location Map - WW2436
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with, Freese and Nichols, Inc for Professional Engineering Design Services for the Virginia Hills Lift Station Abandonment (WW2433), Creek Hollow Lift Station Improvements (WW2434), Erwin Farms Lift Station Abandonment (WW2435), and Sloan Creek Lift Station Improvements (WW2436) and Authorizing Any Necessary Supplemental Agreements

 

Summary

 

COUNCIL GOAL:                     Operational Excellence

                     (2B: Balance available resources to accommodate the growth and maintenance needs of the city)

                     

MEETING DATE:                     June 18, 2024

 

DEPARTMENT:                     Development Services / Engineering

 

CONTACT:                     Katie McKenzie, PE, Engineering CIP Manager

                     Alvin Maliakal, EIT, Graduate CIP Engineer

 

RECOMMENDED CITY COUNCIL ACTION:

                     Approval of Resolution.

 

ITEM SUMMARY:

                     This Resolution authorizes the City Manager to execute a contract in the amount of $257,675, as well as all required supplemental agreements thereto, with Freese and Nichols, Inc. for professional consulting engineering services for the Virginia Hills Lift Station Abandonment (WW2433), Creek Hollow Lift Station Improvements (WW2434), Erwin Farms Lift Station Abandonment (WW2435), and Sloan Creek Lift Station Improvements (WW2436), for a total aggregate contract amount, inclusive of any supplemental agreements, not to exceed $285,000.

 

BACKGROUND INFORMATION:

                     City of McKinney has identified 2 lift stations needing to be abandoned and 2 lift stations needing improvements. The name of the lift stations and locations are as follows:

o                     Lift Station to be Abandoned - Virginia Hills: 1397 Monticello Drive, McKinney TX 75071

o                     Lift Station to be Abandoned - Erwin Farms: 3031 Erwin Farms Blvd, McKinney TX 75071

o                     Lift Station to be Improved - Sloan Creek: 4440 State Hwy 121 S, McKinney TX 75070

o                     Lift Station to be Improved - Creek Hollow: 2405 Avalon Creek Way, McKinney TX 75071

 

                     Freese and Nichols, Inc. submitted a proposal for this project in the amount of $257,675.

                     The preliminary opinion of probable construction cost for improving and demolishing lift stations $977,120.

                     Freese and Nichols, Inc. submitted a response to 21-42 RFQ for on - call utility design services.

 

FINANCIAL SUMMARY:

                     This resolution authorizes a design contract and any necessary supplemental agreements with Freese and Nichols, Inc for an amount not to exceed $285,000.

                     With the approval of this item, following amounts remain with projects below:

o                     WW2433 available Fund 20 (Utlity): $ 185,750.00

o                     WW2434 available Fund 20 (Utlity): $ 527,450.00

o                     WW2435 available Fund 20 (Utlity): $ 177,200.00

o                     WW2436 available Fund 20 (Utlity): $ 1,374,600.00

 

BOARD OR COMMISSION RECOMMENDATION:

                     N/A