Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Construction Contract with Spaw Glass Contractors, Inc. for Construction Services Related to the Design and Construction of the East Louisiana Parking Lot Project (FC2117)
Attachments: 1. Resolution, 2. Proposal, 3. Bid Details

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Construction Contract with Spaw Glass Contractors, Inc. for Construction Services Related to the Design and Construction of the East Louisiana Parking Lot Project (FC2117)

Summary

COUNCIL GOAL:                     Operational Excellence

                     (2B: Balance Available Resources to Accommodate the Growth

                     and Maintenance Needs of the City)

MEETING DATE:                     March 1, 2022

DEPARTMENT:                      Facilities Construction Division

CONTACT:                     Patricia L. Jackson, PE, Facilities Construction Manager                     

RECOMMENDED CITY COUNCIL ACTION:                     

•                     Approval of the Resolution.

ITEM SUMMARY: 

•                     This Resolution authorizes the City Manager to execute a construction services contract to provide complete construction services related to the design and construction of the East Louisiana Parking Lot located in McKinney, Texas 75069.

•                     The selected contractor, Spaw Glass Contractors, Inc. submitted a proposal to provide construction services for the East Louisiana Parking Lot for $2,333,839 which includes the Total Base Bid and Alternate A only. With an added owner’s contingency of $100,000, the not to exceed (NTE) amount is $2,433,839.

BACKGROUND INFORMATION: 

•                     The City issued a Request for Competitive Sealed Proposals (22-19RFCSP) to solicit responses from qualified firms for the construction of the East Louisiana Parking Lot.

o                     Advertised in the McKinney Courier Gazette

o                     Posted on McKinney TV

o                     1,159 Matching eBid Supplier Notifications

o                     Including 50 HUB Supplier Notifications

•                     Out of the 1,159 supplier notifications, nine (9) proposals were received on February 7, 2022.

•                     A committee comprised of Public Works and City Manager’s Office reviewed and ranked the proposals based on the following criteria:

•                     Proposal Scoring - 100 Points Maximum

o                     50 Points- Price & Price Details

o                     25 Points- Firm & Individual Qualifications

o                     10 Points- Reference Letters & Proposed Project Schedule

o                     10 Points- Capability & Capacity to Perform Work

o                     5 Points- Submittal Completeness

 

•                     Spaw Glass Contractors, Inc. is determined to be the top ranked firm after completing the evaluation process.

FINANCIAL SUMMARY: 

•                     The Resolution authorizes the City Manager to execute a small construction services contract for construction services, including potential changes to the scope of services, with Spaw Glass Contractors, Inc. for an amount not to exceed $2,433,839 which includes an owner’s contingency amount of $100,000.

•                     Upon approval of this item, $2,632,543 will remain in the project (FC2117).

BOARD OR COMMISSION RECOMMENDATION:

•                     N/A