Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Garver, LLC for Professional Engineering Design Services for the Arterial Capacity Improvements Project (ST1618) and Any Necessary Supplemental Agreements

 

Summary

 

COUNCIL GOAL:                     Direction for Strategic and Economic Growth

 

MEETING DATE:                     June 20, 2017

 

DEPARTMENT:                     Development Services / Engineering

 

CONTACT:                     Gary Graham, PE, CIP & Transportation Engineering Manager

                     Joshua Cotton, PE, Senior CIP Engineer

 

 

RECOMMENDED CITY COUNCIL ACTION:

•                     Approval of Resolution

 

ITEM SUMMARY:

•                     This Resolution authorizes a contract with Garver, LLC to provide consulting engineering services for the design of the Arterial Capacity Improvements Project (ST1618) for an amount not to exceed $300,000.

 

BACKGROUND INFORMATION:

•                     The intersections of US 380 and Hardin Boulevard, Westridge Boulevard and Custer Road, and Virginia Parkway and Ridge Road are in need of capacity improvements.

•                     At US 380 and Hardin Boulevard, right turn lanes will be added to all approaches along with dual northbound and southbound left turn lanes.

•                     At Westridge Boulevard and Custer Road, an eastbound right turn lane will be added.

•                     At Virginia Parkway and Ridge Road, an additional northbound left turn lane will be added while extending the existing left turn lane along with adding an eastbound right turn lane.

•                     These improvements will also necessitate improvements to and modification of the existing traffic signals at the three intersections.

•                     Garver, LLC submitted a response to RFQ 15-38 for Roadway Design.  They were one of ten firms shortlisted by City Council on October 20, 2015.

•                     Garver, LLC submitted a proposal for this project in the amount of $269,215.

•                     The preliminary opinion of probable construction cost is $2,105,500.

•                     The fee for basic services is $188,841 (9.0% of the construction cost) and the fee for special services is $80,374 (3.8% of the construction cost).

 

FINANCIAL SUMMARY:

•                     This Resolution authorizes a design contract and any necessary supplemental agreements with Garver, LLC for an amount not to exceed $300,000.

•                     With the approval of this item, $1,700,000 will remain in project ST1618.

 

BOARD OR COMMISSION RECOMMENDATION: