Legislation Details

File #: 17-314    Name: Newsome Homes Loan Extension
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 3/21/2017 Final action: 3/21/2017
Title: Consider/Discuss/Act on a Resolution Approving an Amendment to the McKinney Housing Authority (MHA) Revolving Loan for Newsome Homes Redevelopment Pursuant to a Chapter 393 Loan Agreement Between the City of McKinney and the McKinney Housing Authority
Attachments: 1. Resolution, 2. Construction Delay Documentation, 3. Newsome - Sources and Uses, 4. MHA Newsome Home Agreement - Redline

title

Consider/Discuss/Act on a Resolution Approving an Amendment to the McKinney Housing Authority (MHA) Revolving Loan for Newsome Homes Redevelopment Pursuant to a Chapter 393 Loan Agreement Between the City of McKinney and the McKinney Housing Authority

 

Summary

 

COUNCIL GOAL:                     Improve the Quality of Life in McKinney

 

MEETING DATE:                     March 21, 2017

 

DEPARTMENT:                      Housing and Community Development

 

CONTACT:                       Janay Tieken, Housing and Community Development

                     

 

RECOMMENDED CITY COUNCIL ACTION:                     

•                     Approve a Resolution extending the Borrower’s (MHA) loan performance period for qualified expenditures until October 1, 2017 and amending all applicable sections under the loan agreement and Chapter 393 agreement.

 

ITEM SUMMARY: 

•                     The McKinney Housing Authority (MHA) is requesting a six (6) month extension of the performance period for qualified expenditures from April 1, 2017 to October 1, 2017.

•                     “Qualified Expenditures” are certain defined and budgeted construction expenses made incident to the Newsome Homes project.

•                     Final loan disbursement of $385,350 will be made on March 1, 2018 based on qualified expenditures made through October 1, 2017

 

BACKGROUND INFORMATION: 

•                     Original loan authorization and Chapter 393 agreement was approved on August 4, 2014, Resolution # 0214-08-90.

•                     Borrower is requesting a loan compliance extension request based on documented construction delays.

•                     Chapter 393 of the Local Government Code allows the City to provide a low interest, revolving loan facility for a portion of the request. The loan was approved with the following terms:

o                     Principal Amount: $1,156,052

o                     Interest Rate: 2.75%

o                     First advance: $116,000 park fees at issuance of building permit

o                     Second Advance: $269,350 on March 1, 2016

o                     Third Advance: $385,350 on March 1, 2017

o                     Fourth Advance: $385,350 on March 1, 2018

o                     Repayment: $25,000 annual payments beginning on November 1, 2020 through November 1, 2030; then increasing to $50,000 from November 1, 2031 through November 1, 2035; then increasing to $100,000 from November 1, 2036 to November 1, 2039; and with a final payment of the balance of principal and interest due on November 1, 2040.

o                     Payments will remain in the revolving fund for future MHA projects, as available, and upon qualifying and as approved by the City Council.

o                     Loan will contain a savings provision whereby City and Developer will share savings below an agreed GMP.

•                     The MHA’s annual payment-in-lieu of taxes to the City will also be waived during the term of the loan.

•                     Project Sources and Uses as of 7/29/14 are attached.

 

FINANCIAL SUMMARY:

 

 

 

BOARD OR COMMISSION RECOMMENDATION: N/A