Consider/Discuss/Act on a Resolution Awarding a Contract to WaterCentric, LLC of Carrollton, Texas and A N D, INC. dba A New Deal Irrigation of Wylie, Texas for Irrigation Services: Repair and Installation
 
Summary
 
COUNCIL GOAL:   Operational Excellence
(2B: Balance available resources to accommodate the growth and maintenance needs of the city)
 
MEETING DATE:                     May 3, 2022
 
DEPARTMENT:                      Parks and Recreation Department 
 
CONTACT:                       Michael Kowski, Director of Parks and Recreation
                     Marty Sillito, Parks Superintendent
                     Keith Biggs, Parks Maintenance Supervisor 
 
 
RECOMMENDED CITY COUNCIL ACTION:                     
•                     Approval of Resolution
 
ITEM SUMMARY:  
•                     This Resolution authorizes an award of a fixed price contract with WaterCentric, LLC and A N D, INC. dba A New Deal Irrigation for as needed Irrigation Repair and Installation Services.
 
BACKGROUND INFORMATION:  
•                     The City issued Invitation to Bid 22-25FP Irrigation Services: Repair and Installation on March 13, 2022.
o                     Advertised in McKinney Courier Gazette
o                     Posted on McKinney TV
o                     434 matching eBid Supplier Notifications
o                     Out of 434 notifications, twenty (20) were Historically Underutilized Businesses (HUB)
 
•                     In response to all notices published, three (3) bids were received on March 31, 2022.
 
•                     An evaluation team comprised of staff from Parks and Recreations reviewed and ranked the bids based on the following criteria:
o                     70 Points: Purchase Price
o                     30 Points: Response Time
 
•                     The evaluation team recommends awarding WaterCentric, LLC as the primary contractor and A N D, INC. dba A New Deal Irrigation as the secondary contractor. 
 
•                     Staff recommends a primary and a secondary contractor to help streamline and expedite projects and avoid project delays.
 
•                     Contract will commence on date of award and continue for a one (1) year period with two (2) one- year renewal options.
 
FINANCIAL SUMMARY:  
•                     Funding for these as needed services is budgeted in multiple FY22 approved accounts.
 
 
BOARD OR COMMISSION RECOMMENDATION:
•                     N/A
 
 
SUPPORTING MATERIALS:
 
Resolution
Scoring Summary
Bid Tabulation