Legislation Details

File #: 11-275    Name: Intersections - Construction
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 6/7/2011 Final action: 6/7/2011
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Jim Bowman Construction Company, LP, for Construction Services for Intersection Improvements at Seven Locations on Virginia Parkway and Eldorado Parkway
Attachments: 1. Resolution, 2. Bid Tabulations, 3. Location Map

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Jim Bowman Construction Company, LP, for Construction Services for Intersection Improvements at Seven Locations on Virginia Parkway and Eldorado Parkway

 

Summary

 

MEETING DATE:                     June 7, 2011

 

DEPARTMENT:                      Development Services / Engineering

 

CONTACT:                       Matt Richardson, P.E., CIP Manager

 

 

RECOMMENDED CITY COUNCIL ACTION:                     

•                     Approval of the Resolution. 

 

ITEM SUMMARY: 

•                     This item authorizes the City Manager to execute a contract with Jim Bowman Construction Company, LP, for the construction of intersection improvements at seven locations for an amount not-to-exceed $3,200,000. 

 

BACKGROUND INFORMATION: 

•                     This project includes the construction of right-turn lanes, left-turn lanes, and traffic signal improvements at the following locations:

o                     Virginia Parkway and Hardin Boulevard

o                     Virginia Parkway and Lake Forest Drive

o                     Eldorado Parkway and Hardin Boulevard

o                     Eldorado Parkway and Lake Forest Drive

o                     Eldorado Parkway and Ridge Road

o                     Eldoardo Parkway and Alma Road

o                     Eldorado Parkway and Stonebridge Drive

•                     This project also includes the construction of 140 feet of a 20-inch water main crossing Stonebridge Drive at Eldorado Parkway. 

•                     Five bids were received on May 19, 2011, with Jim Bowman Construction Company, LP, being the lowest responsive bidder:

o                     Jim Bowman Construction                                          $2,876,183.20

o                     JRJ Paving                                                                                    $3,000,806.44

o                     Tiseo Paving                                                                                    $3,124,985.39

o                     Fain Group                                                                                    $3,572,691.85

o                     XIT Paving                                                                                    $3,624,239.46

•                     Jim Bowman Construction is based in Plano and has previously worked for the City on the Virginia Street Reconstruction and on various pavement rehabilitation projects. 

•                     The contract allows 450 days for construction, which is approximately two months per intersection. 

•                     The contract specifies that only one intersection is to be under construction at any given time, although the contractor may propose alternate phasing plans for staff review. 

 

FINANCIAL SUMMARY: 

•                     Funding for this contract is available in the Capital Improvements Program, ST7128 ($3,000,000) and WA0208 ($200,000).

 

BOARD OR COMMISSION RECOMMENDATION:

•                     N/A