Legislation Details

File #: 26-0747    Name: Garver Contract for Taxiway C Phase II and III Design
Type: Resolution Status: Consent Item
In control: City Council Regular Meeting
On agenda: 8/4/2026 Final action:
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Garver, LLC, for Design and Related Professional Services for Phase II and Phase III of the McKinney National Airport Taxiway C Project (AI2721 & AI2722), Contingent upon Receipt of FAA Airport Improvement Program Grant Funding
Attachments: 1. Resolution, 2. Proposal, 3. Form 1295
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Garver, LLC, for Design and Related Professional Services for Phase II and Phase III of the McKinney National Airport Taxiway C Project (AI2721 & AI2722), Contingent upon Receipt of FAA Airport Improvement Program Grant Funding

Summary

COUNCIL GOAL:                       Maximize the Development Potential of McKinney National Airport

                     3.1:  Implement initiatives and strategies, including public-private partnerships, to attract and expand corporate and commercial aviation including the viability of passenger service.

                     3.2: Identify and implement land use regulations and policies that preserve and expand long-term operational excellence.

MEETING DATE: August 4, 2026

DEPARTMENT: Airport

CONTACT: Kenneth Carley, A.A.E., Airport Director

RECOMMENDED ACTION:

                     Staff recommends City Council approve this item.

ITEM SUMMARY:

                     Garver, LLC has submitted a professional services proposal to provide design and related professional services for the extension of Taxiway C from the commercial terminal apron to the end of Runway 18.

                     The improvements are needed to extend Taxiway C to enhance safety of operations, while evaluating the runway safety area for conformance with FAA Advisory Circular 150/5300-13B, and prepare the airport for planned future development.

                     The scope includes preparing a preliminary engineering report, detailed construction drawings, specifications, instructions to bidders, general and special provisions, contract documents (plans, specifications, and estimates), surveying, geotechnical investigation, and design through 90% and 100% completion levels.

                     Execution of the contract is contingent upon the City's receipt of FAA Airport Improvement Program Grant funding. A 10% match of $304,000 will be appropriated as part of the grant.

BACKGROUND INFORMATION:

                     Garver was selected to serve as the Airport's Engineer of Record through a formal RFQ process

                     Garver, LLC will serve as the prime design consultant, with subconsultant support from White Hawk Engineering (surveying), Terracon (geotechnical services), and Alder Airfield Services (airfield escort services).

                     Garver anticipates completing the Preliminary Engineering Report within 8 weeks of Notice to Proceed, with 90% Final Design submittals following 8 weeks after receipt of Owner and FAA comments, and the 100% Issued for Bid package for Phase II following 4 weeks after receipt of comments.

FINANCIAL SUMMARY:

                     The not-to-exceed fee for Garver's Title I design services for Taxiway C Phase II and Phase III is $3,040,000.00, as detailed below:

Fee Component

Amount

Surveys (White Hawk Engineering)

$165,000.00

Geotechnical (Terracon)

$77,500.00

Airfield Escort (Alder)

$81,000.00

Preliminary Engineering Report - Phase II and Phase III

$493,500.00

90% Design - Phase II

$778,000.00

100% Issued for Bid - Phase II

$575,000.00

Bidding Services - Phase II

$30,000.00

90% Design - Phase III

$840,000.00

Total (Not-to-Exceed)

$3,040,000.00

                     Funding is proposed through FAA Airport Improvement Program Grant funding; execution of the contract is contingent upon the City's receipt of this grant funding.

                     A budget amendment may be required to appropriate grant funds upon award.

                     A required 10% match of $304,000 will be appropriated as part of the grant.