File #: 10-003    Name: Railroad Track Repair Work
Type: Resolution Status: Consent Item
In control: Engineering
On agenda: 1/5/2010 Final action: 1/5/2010
Title: Consider/Discuss/Act on a Resolution Authorizing a Contract for Railroad Track Repair Work along the Dallas Area Rapid Transit (DART) Railroad Line near Railroad Street and Smith Street
Attachments: 1. Resolution, 2. Location Map

Title

Consider/Discuss/Act on a Resolution Authorizing a Contract for Railroad Track Repair Work along the Dallas Area Rapid Transit (DART) Railroad Line near Railroad Street and Smith Street

Summary

 

MEETING DATE:                      January 5, 2010

 

DEPARTMENT:                      Development Services / Engineering

 

CONTACT:                                           Jack Carr, PE, Director of Engineering

                                          Rob Daake, PE, CIP Manager

                                          Danny Still, PE, Graduate Engineer

 

 

RECOMMENDED CITY COUNCIL ACTION:

                     Approval of Resolution.

 

ITEM SUMMARY:

                     This resolution authorizes a contract with Dallas, Garland, and Northeastern Railroad, Inc., (DGNO) for railroad track repair work along the DART railroad line near Railroad Street and Smith Street, for an amount not to exceed $64,000.

 

BACKGROUND INFORMATION:

                     The Capital Improvements Program includes a project for the reconstruction of the streets in the vicinity of Smith Street and Railroad Street.

                     This project required the construction of double 10 x 4 box culverts crossing under the railroad.

                     In August 2008, during the construction of these box culverts, a significant rain event flooded the area resulting in a slope failure at the DART railroad embankment.

                     The embankment was temporarily shored with steel beams and steel plates to stabilize the slope failure area until a permanent solution was developed.

                     A repair plan that involves removing and recompacting the unstable soil has been accepted by all parties.

                     This contract includes the removal and replacement of a section of track as necessary to allow the recompaction work to occur.

                     The railroad property is owned by DART and the rail is operated and maintained by DGNO; therefore, DGNO has submitted a proposal, in the amount of $53,565.66, to perform this work.

 

FINANCIAL SUMMARY:

                     This resolution authorizes a contract with DGNO, for an amount not to exceed $64,000.

Because of the age of the track that is being removed and replaced, some of the materials may not be suitable to be reused; therefore, the contingency amount is larger than normal to allow for some new material to be incorporated into the project as necessary.

Funds are available in the Capital Improvements Program in CO2115.

 

BOARD OR COMMISSION RECOMMENDATION:

N/A