Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to execute a Federal Aviation Administration (FAA) Reimbursable Agreement for the relocation and construction on the Runway 18 NAVAIDS as part of the McKinney National Airport Project AI2452, Extend Runway 18 | Phase 1 - 500' North
Attachments: 1. Resolution, 2. 21-SW-004594 TKI Final_8.20.24

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to execute a Federal Aviation Administration (FAA) Reimbursable Agreement for the relocation and construction on the Runway 18 NAVAIDS as part of the McKinney National Airport Project AI2452, Extend Runway 18 | Phase 1 - 500’ North

 

Summary

 

COUNCIL GOAL:                     Maximize the Development of McKinney National Airport

 

                     3A: Implement initiatives and strategies, including public-private partnerships, to attract and expand corporate and commercial aviation including the viability of passenger service.

                     3B: Identify and implement land use regulations and policies that preserve and expand long-term operational excellence.

 

MEETING DATE:                     September 17, 2024

 

DEPARTMENT:                      Airport

 

CONTACT:                       Ken Carley, Airport Director

 

 

RECOMMENDED CITY COUNCIL ACTION:                     

                     Approve Resolution

 

ITEM SUMMARY: 

                     The Resolution authorizes the City Manager to execute a Federal Aviation Administration (FAA) Reimbursable Agreement for the relocation and construction on the Runway 18 NAVAIDS as part of the McKinney National Airport Project AI2452, Extend Runway 18 | Phase 1 - 500’ North.

 

BACKGROUND INFORMATION: 

                     The proposed scope of work for this Agreement between the Federal Aviation Administration (FAA) and the City of McKinney (Sponsor) is to perform site visit, preliminary design and engineering review, and construction/installation activities in the Sponsor’s project to extend Runway (RWY) 18 and Taxiway (TWY) B impacting FAA NAS facilities including the RWY 18 Medium-Intensity Approach Lighting System with Runway Alignment Indicator (MALSR), RWY 18 Glideslope, and associated FAA cabling and infrastructure.

 

FINANCIAL SUMMARY: 

                     The City of McKinney is required to prepay the total estimated cost of $749,586.47.

                     Upon approval of this item and companion items, the remaining balance in AI2452 will be $3,748,706.41.

                     The companion agenda items are on the September 17, 2024, City Council agenda for the Garver LLC construction phase services and the construction bid award to RPMx for project AI2452.

 