Legislation Details

File #: 16-020    Name: Public Safety Facility Phase 3 A/E Contract
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 1/5/2016 Final action: 1/5/2016
Title: Consider/Discuss/Act on a Resolution Authorizing the Interim City Manager to Execute a Professional Services Contract with Brinkley, Sargent, Wiginton Architects of Dallas, Texas for Architectural and Engineering Services Related to the Design and Construction of Phase 3 of the Public Safety Facility
Attachments: 1. Resolution, 2. Proposed Contract

Title

Consider/Discuss/Act on a Resolution Authorizing the Interim City Manager to Execute a Professional Services Contract with Brinkley, Sargent, Wiginton Architects of Dallas, Texas for Architectural and Engineering Services Related to the Design and Construction of Phase 3 of the Public Safety Facility

 

Summary

 

COUNCIL GOAL:                     Safe and Secure Community

 

MEETING DATE:                     January 5, 2016

 

DEPARTMENT:                      Public Works / Fire Department

 

CONTACT:                       Patricia L. Jackson, P.E., Facilities Construction Manager

                     Greg Conley, Chief of Police

                     Danny Kistner, Fire Chief

 

 

RECOMMENDED CITY COUNCIL ACTION:                     

•                     Approval of the Resolution.

 

ITEM SUMMARY: 

•                     This Resolution authorizes a professional services contract to provide complete architectural and engineering services related to the master planning and design and construction of Phase 3 of the Public Safety Building located at 2200 Taylor-Burk Drive.

•                     The selected consultant team, Brinkley, Sargent, Wiginton Architects (BSW), submitted a proposal to provide professional architectural and engineering services for the Phase 3 of the Public Safety Building for $679,125.

 

BACKGROUND INFORMATION: 

•                     Nine firms submitted Statements of Qualifications on October 1, 2015 and were evaluated by members of the McKinney Police and Fire departments along with staff from the Development Services department.

•                     From the nine firms that submitted, the four highest ranked architectural and engineering teams were interviewed.

•                     After interviews, the firm of Brinkley, Sargent, Wiginton Architects was selected as the top ranking team.

•                     Brinkley, Sargent, Wiginton Architects is an award winning professional architectural consulting services firm based in Dallas, Texas that specializes in public architecture.

•                     Brinkley, Sargent, Wiginton Architects has performed successfully for the City of McKinney on several previous projects.

 

FINANCIAL SUMMARY: 

•                     Public Safety Building Phase 3 (FC2229) was funded in the FY14-15 Capital Improvements Program with $7,350,000 of general obligation bonds from the 2006 and 2010 elections.

•                     The Resolution authorizes a professional services contract for architectural and engineering services, including potential changes to the scope of services, with Brinkley, Sargent, Wiginton Architects for an amount not to exceed $735,000.

 

BOARD OR COMMISSION RECOMMENDATION: N/A