Consider/Discuss the Crossing at State Highway 5

 

Summary

 

COUNCIL GOAL:                     Operational Excellence

                     (2.1: Balance available resources to accommodate the growth and maintenance needs of the city)

                     

MEETING DATE:                     July 7, 2026

 

DEPARTMENT:                     Development Services / Engineering

 

CONTACT:                     Gary Graham, Director of Engineering

                     Blake Sills, PE, Engineering CIP Manager

                     

RECOMMENDED CITY COUNCIL ACTION:

                     Receive a presentation and discuss items related to the Crossing at State Highway 5 Project.

 

ITEM SUMMARY:

                     Discuss items related to the ongoing development of the State Highway 5 project.

 

BACKGROUND INFORMATION:

                     Texas Department of Transportation’s (TxDOT) design for SH 5 roadway improvements from McMakin Street to Power House Street is underway, referenced as CSJ 0047-05-054. The planned improvements to SH 5 include a complete reconstruction as a 4-lane divided roadway. Construction of the planned improvements is estimated to begin in late 2027 or early 2028 following City of McKinney water/wastewater and Franchise Utilities’ relocations.

                     The Lower 5 Plaza has been removed from the project. Staff is coordinating with TxDOT on enhancements to the standard treatments TxDOT applies to these types of projects.

                     The City’s Capital Improvements Program includes the following improvements to be incorporated into TxDOT’s roadway construction for SH 5 from McMakin Street to Power House Street:

o                     Continuous median-mounted roadway lighting and City of McKinney median conduit systems for illumination, irrigation, and fiber conduit

o                     Underground drainage systems upgraded from TxDOT’s 5-Year storm design to 50-Year storm design to meet the City of McKinney’s design criteria

o                     Turn lanes and colored textured concrete in lieu of TxDOT’s standard rock riprap on medians along SH 5

o                     Enhanced noise wall aesthetic treatments

                     An updated presentation has been prepared covering the following areas:

o                     Project Overview

o                     Summary of Public Outreach

o                     Funding

o                     Next Steps

                     Staff is presenting this informational presentation to receive concurrence on direction as we continue to coordinate with NCTCOG and TxDOT to incorporate the improvements along SH 5 between McMakin Street and Power House Street.