Legislation Details

File #: 24-1589    Name: Wilson Creek Greens Trail Construction Contract
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 5/21/2024 Final action: 5/21/2024
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract and All Necessary Change Orders with A & C Construction, Inc. of Irving, Texas, for Construction of the Wilson Creek Greens Trail Project (PK1827)
Attachments: 1. Resolution

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract and All Necessary Change Orders with A & C Construction, Inc.  of Irving, Texas, for Construction of the Wilson Creek Greens Trail Project (PK1827)

 

Summary

 

COUNCIL GOAL:                     Enhance the Quality of Life in McKinney                                                               

(5A: Create affordable recreational and cultural arts activities for all ages throughout the city)

(5B: Develop Parks strategy to preserve green space for future park land)

(5C: Continue to market and highlight McKinney as a unique destination for residents and visitors alike)

(5E: Develop sustainable quality of life improvements within the City of McKinney)

 

 

MEETING DATE:                     May 21, 2024

 

DEPARTMENT:                      Parks and Recreation

 

CONTACT:                       Amy Kinkade, Director of Parks and Recreation

 

RECOMMENDED ACTION:                     

•                     Approval of the Resolution

 

ITEM SUMMARY: 

•                     This Resolution authorizes the City Manager to execute a contract and all necessary change orders with A & C Construction, Inc. of Irving, Texas for the construction of the Wilson Creek Greens Trail Project (PK1827) for a total contract amount not to exceed $1,130,000.00.

 

•                     City staff worked with LJA Engineering, Inc. on preparing the construction plans and specifications as needed for project bidding.

 

•                     Staff, along with LJA Engineering, Inc. support, recommends awarding the construction bid to A & C Construction, Inc. in an amount of $1,069,970.00 along with a $60,030.00 contingency for a total not to exceed amount of $1,130,0000.00

 

BACKGROUND INFORMATION: 

•                     This proposed trail project will connect the existing Wilson Creek trailhead on the north side of Eldorado Parkway to McKinney Greens parkland.  This is a critical connection that will provide a continuous pedestrian connection from this park all the way to our parkland near Lake Forest Drive.

•                     The proposed project will provide connectivity between Towne Lake and the McKinney Greens parkland and include amenities such as:

o                     Trail improvements

o                     Bridge crossings

o                     Trail overlook

o                     Site furnishings

 

•                     The City issued Invitation to Bid 24-22CSP, Construction of Wilson Creek Greens Trail on March 31, 2024.

o                     Advertised in McKinney Courier Gazette

o                     Posted on McKinney TV

o                     1223 matching eBid Supplier Notifications

o                     58 Historically Underutilized Business (HUB) Vendors were notified.

 

•                     In response to all notices published, nine (9) bids were received on April 25, 2024, from:

o                     A & C Construction Inc.

o                     AT Construction

o                     HQS Construction, LLC

o                     ALCC, LLC dba Perfect Finish Landscaping

o                     Ratliff Hardscape, Ltd

o                     T.F. Harper & Associates, LP

o                     The Fain Group, Inc

o                     Dustin M. Wall dba Wall Contractors, LLC

o                     Waterfalls Construction LLC

 

•                     Submissions were evaluated on the following criteria:

o                     25 Points - Capability to Perform Work

o                     35 Points - Contractor and Subcontractor Qualifications

o                     40 Proposal Price

 

•                     Upon approval, construction should begin in June 2024 with a 240-day contract schedule.

 

FINANCIAL SUMMARY: 

•                     This project (PK1827) is a FY23-24 Capital Improvements Program funded by MCDC funds and grant monies.

 

•                     Upon approval of this item, $3,683.681.00 will remain in PK1827

 

•                     In 2019, this project was awarded a $396,000 matching grant from the Collin County Open Space program.

 

BOARD OR COMMISSION RECOMMENDATION:

•                     On May 9, 2024, the Parks, Recreation and Open Space Advisory Board recommended to City Council the award of the construction contract.