Legislation Details

File #: 11-308    Name: LPAFA Deceleration Lanes
Type: Resolution Status: Approved and Finalized
In control: City Council Regular Meeting
On agenda: 6/21/2011 Final action: 6/21/2011
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Enter into a Local Project Advance Funding Agreement (LPAFA) with the Texas Department of Transportation (TxDOT) to Construct Right-Turn Deceleration Lanes Related to the Reconstruction of US 380 from Lake Forest Drive to Custer Road (FM 2478)
Attachments: 1. Resolution, 2. Location Map

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Enter into a Local Project Advance Funding Agreement (LPAFA) with the Texas Department of Transportation (TxDOT) to Construct Right-Turn Deceleration Lanes Related to the Reconstruction of US 380 from Lake Forest Drive to Custer Road (FM 2478)

 

Summary

 

MEETING DATE:                     June 21, 2011

 

DEPARTMENT:                      Development Services/Engineering

 

CONTACT:                       Corey Nesbit, P.E., Development Engineering Manager

                     Jack Carr, P.E., Director of Engineering

 

 

RECOMMENDED CITY COUNCIL ACTION:                     

•                     Approval of the Resolution.

 

ITEM SUMMARY: 

•                     This Resolution authorizes the City Manager to enter into a Local Project Advance Funding Agreement (LPAFA) with the Texas Department of Transportation (TxDOT) for the construction of two right-turn deceleration lanes on US 380 as necessary for the development of the southwest corner of US 380 and Lake Forest Drive, for an amount not to exceed $65,000.

 

BACKGROUND INFORMATION: 

•                     TxDOT is preparing to widen the section of US 380 between Lake Forest Drive and Custer Road by adding a lane to the outer edge of the existing roadway.

•                     The US 380 widening project will be let in July 2011 and is scheduled to be completed in 2014.

•                     Construction plans for the development of the tract of land at the southwest corner of the intersection of US 380 and Lake Forest Drive have been submitted for approval.

•                     The development project includes the construction of two driveways that will connect to US 380, both of which require right-turn deceleration lanes.

•                     If the right-turn deceleration lanes are constructed with the current lane configuration on US 380, the work would not be compatible with the proposed  US 380 widening project.

•                     TxDOT, City Staff, and the developer agree that it would be better to not construct the right-turn deceleration lanes prior to the TxDOT project and two better options are:

o                     Construct the right-turn deceleration lanes after the TxDOT project is completed.

o                     Include the construction of the right-turn deceleration lanes with the TxDOT project.

•                     Of the two options, the best option is to construct the right-turn deceleration lanes as part of the TxDOT project.

•                     TxDOT cannot enter into an agreement directly with a developer; therefore, if this option is chosen, the City would enter into a Local Project Advance Funding Agreement (LPAFA) with TxDOT for payment of the cost to complete the right-turn deceleration lanes, using funds provided by the developer. 

•                     TxDOT has prepared a LPAFA that addresses the construction of the two right-turn deceleration lanes as part of their roadway widening project.

•                     The developer has agreed to the cost estimate for TxDOT constructing the right-turn deceleration lanes and has agreed to execute a standard facilities agreement.

•                     The developer will be required to provide the funds to the City prior to the City executing the LPAFA.

 

FINANCIAL SUMMARY: 

•                     TxDOT will construct the two right-turn deceleration lanes using funds provided by the developer; therefore, no City funds are required for this agreement.

•                     A concurrent Budget Amendment for project ST9158 identifies the developer as the funding source for this agreement.

 