Legislation Details

File #: 16-175    Name: Ash Woods Construction Budget Amendment
Type: Ordinance Status: Approved
In control: City Council Regular Meeting
On agenda: 2/16/2016 Final action: 2/16/2016
Title: Consider/Discuss/Act on an Ordinance Amending the Fiscal Year 2015-2016 Annual Budget and Amending the 2016 - 2020 Capital Improvements Program, to Provide Funds for the Ash Woods Park Pedestrian Bridge Project (PK4368)
Attachments: 1. Ordinance

Title

Consider/Discuss/Act on an Ordinance Amending the Fiscal Year 2015-2016 Annual Budget and Amending the 2016 - 2020 Capital Improvements Program, to Provide Funds for the Ash Woods Park Pedestrian Bridge Project (PK4368)

 

Summary

 

COUNCIL GOAL:                     Financially Sound Government

 

MEETING DATE:                     February 16, 2016

 

DEPARTMENT:                      Parks and Recreation Department

                     

CONTACT:                       Rhoda L. Savage, Director of Parks and Recreation

 

 

 

RECOMMENDED CITY COUNCIL ACTION:                     

•                     Approval of the Ordinance.

 

ITEM SUMMARY: 

•                     This Ordinance amends the FY2015-2016 annual CIP budget and the 2016 - 2020 Capital Improvement Program, by increasing the budget by $48,320 by transferring $24,160 from the Parkland Dedication Zone 3 Fund and $24,160 for ISD Contributions to the Parks Construction Fund and appropriating the funds to CIP project PK4368 Ash Woods Park Hike and Bike Trail Bridge Project.

 

BACKGROUND INFORMATION: 

•                     Project design and bidding have been completed.

 

•                     The ability to award the bid is contingent on amending the project budget as proposed.

 

•                     Through an associated Interlocal Agreement (ILA), the cities of McKinney, Frisco and the Frisco Independent School District agreed to a joint project to construct pedestrian walkways and a pedestrian bridge over an existing drainage swale in Ash Woods Park.

 

•                     McKinney’s agreed portion of the project was estimated to cost $160,000, of which FISD will fund half.  The following is the breakdown of the estimated cost.

 

 

 

 

 

 

City 50% share

FISD 50% share

Estimated Consultant Fee

 $        40,000.00

 $        20,000.00

 $           20,000.00

Estimated Construction Fee

 $      120,000.00

 $        60,000.00

 $           60,000.00

Estimated Budget

 $      160,000.00

 $        80,000.00

 $           80,000.00

 

•                     The actual cost is $208,320 with the break down as follows:

Actual Cost

 

City 50% share

FISD 50% share

Architectural and Engineering Design Fees

 $   38,750.00

 $   19,375.00

 $      19,375.00

Land Acquisition Fees

 $     4,120.00

 $     2,060.00

 $        2,060.00

Materials Testing

 $     8,895.00

 $     4,447.50

 $        4,447.50

Construction Contract

 $156,555.00

 $   78,277.50

 $      78,277.50

Total Cost

 $208,320.00

 $104,160.00

 $    104,160.00

 

•                     An additional amount of $24,160 is required of each party from the original estimated amount.

 

•                     FISD’s board approved their portion of the project funding on February 8, 2016 in an amount of $104,160.

 

•                     FISD’s funds will be provided once the work has been completed as a reimbursement to the City.

 

•                     Finally, an amount of $16,000 was previously approved in the budget to cover a 10% project construction contingency.  These funds may / or may not be expended and therefore is not reflected as a shared cost at this time.

 

•                     An accompanying Resolution to enter into a construction contract is also on this agenda for Council’s consideration.

 

FINANCIAL SUMMARY: 

•                     This Ordinance amends the FY2015-2016 annual CIP budget and the 2016 - 2020 Capital Improvement Program, by increasing the budget by $48,320 by transferring $24,160 from the Parkland Dedication Zone 3 Fund and $24,160 for ISD Contributions to the Parks Construction Fund and appropriating the funds to CIP project PK4368 Ash Woods Park Hike and Bike Trail Bridge Project.

BOARD OR COMMISSION RECOMMENDATION: N/A