Legislation Details

File #: 26-1008    Name: Safe Street McKinney CSAP
Type: Agenda Item Status: Agenda Ready
In control: City Council Work Session
On agenda: 10/20/2026 Final action:
Title: Consider/Discuss the Safe Streets McKinney Comprehensive Safety Action Plan Final Report and Next Steps
Attachments: 1. Plan, 2. Presentation
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Consider/Discuss the Safe Streets McKinney Comprehensive Safety Action Plan Final Report and Next Steps

 

Summary

 

COUNCIL GOAL:                     Operational Excellence

(2.2: Continuously provide a high level of customer service to our citizens.)

 

                     Enhance the Quality of Life in McKinney

(5.5: Enhance connectivity to parks & civic facilities, schools/education centers, libraries, health care providers, commercial corridors, etc.)

 

                     Safe & Secure Community

(6.2: Maintain meaningful public safety performance measurements.)

 

 

MEETING DATE:                     October 20, 2026

 

DEPARTMENT:                      Development Services / Engineering

 

CONTACT:                       Gary Graham, PE, PTOE, Director of Engineering

                     Pamela Alummoottil, PE, PTOE, Traffic Engineer

 

 

 

RECOMMENDED CITY COUNCIL ACTION:                     

•                     Staff recommends that the City Council provide Engineering feedback on the Comprehensive Safety Action Plan (CSAP) before a tentative adoption in November 2026.

 

ITEM SUMMARY: 

•                     Engineering will provide a summary of the Comprehensive Safety Action Plan (CSAP). The latest version of Safe Streets McKinney CSAP can be found at McKinneyTexas.org/SafeStreets <https://www.mckinneytexas.org/safestreets>.  A resolution is planned to be presented to Council in November 2026 for the adoption of the Safe Streets McKinney CSAP.

 

BACKGROUND INFORMATION: 

•                     In December 2023, City Council approved resolution no. 2023-12-163 authorizing the City Manager to accept a federal grant to develop a CSAP through the Safe Streets and Roads for All (SS4A) Grant Program.

•                     The FY25 Capital Improvement Plan budget includes funding under CIP Project ST2463 to develop the CSAP, which includes $240,000 in federal funds and $60,000 in local match funds.

•                     Fehr & Peers submitted a response to 24-14RFQ Category IV - Traffic Studies/Services and was selected from this group based on qualifications to conduct the CSAP. A notice to proceed was issued December 2024.

•                     Based on the USDOT Grant Agreement Amendment, the CSAP is required to be completed and adopted by Council by November 30, 2026.

 

 

FINANCIAL SUMMARY: 

•                     N/A

 

BOARD OR COMMISSION RECOMMENDATION:

•                     N/A