File #: 24-1992    Name: Runway 18 Extension
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 9/17/2024 Final action: 9/17/2024
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract and All Necessary Change Orders with RPMx Construction, LLC for the Construction of Runway 18 Extension (500-Foot)
Attachments: 1. Resolution, 2. Letter of Recommendation

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract and All Necessary Change Orders with RPMx Construction, LLC for the Construction of Runway 18 Extension (500-Foot)

 

Summary

 

COUNCIL GOAL:                     [Operational Excellence

(2B: Balance available resources to accommodate the growth and maintenance needs of the city)

 

MEETING DATE:                     September 17, 2024

 

DEPARTMENT:                      McKinney National Airport

                     Procurement Services

 

CONTACT:                       Kenneth Carley, Director of Airport

                     Erika Roberts, Buyer II

 

 

RECOMMENDED CITY COUNCIL ACTION:                     

                     Approval of Resolution

 

ITEM SUMMARY: 

                     This Resolution authorizes the City Manager to execute a contract and all necessary change orders with RPMx Construction, LLC for the Construction of Runway 18 Extension (500-foot) project for a total contract amount not to exceed $24,000,000.00

                     This is part of project Al2452, Runway 18 Extension 18 (500-foot)

 

BACKGROUND INFORMATION: 

                     Garver, LLC prepared the construction plans for the Runway 18 Extension (500-foot).

                     The City issued an Invitation to Bid (24-29CC) to solicit responses from qualified contractors for the Construction of Runway 18 Extension (500-foot) on June 23, 2024.

o                     Advertised in McKinney Courier Gazette and Celina Record

o                     Posted on McKinney TV

o                     285 matching eBid supplier notifications which included 16 Historically Underutilized Business (HUB) suppliers.

                     Out of the 285 matching supplier notifications, three (3) bids were received and opened by Procurement Services on August 08,2024. The following is a summary of the bids:

 

Bid #

Bidder

Base Bid

Alternate

Total

1

RPMx Construction, LLC

$19,970.054.00

$1,609,620.00

$21,579,674.00

2

Mario Sinacola & Sons, Inc.

$20,335,318.32

$1,493,194.50

$21,848,512.82

3

Reyes TX, Inc.

$23,808,247.00

$2,188,015.30

$25,966,262.30

 

 

                     RPMx Construction, LLC submitted references and qualifications that were evaluated in accordance with the bid specifications as noted in the attached Letter of Recommendation from Garver, LLC dated August 22, 2024.

                     The Airport recommends awarding RPMx Construction, LLC the construction contract for the Runway 18 Extension (500-foot) project.

 

FINANCIAL SUMMARY: 

                     This Resolution authorizes a contract and all necessary change orders with RPMx Construction, LLC for an amount not to exceed $24,000,000.00.

                     Funding for this project is in CIP project Al2452, Runway 18 Extension (500-foot)

                     Upon approval of this item, $3,748,706.41 will remain in Al2452 project

 

BOARD OR COMMISSION RECOMMENDATION:

                     N/A

 

SUPPORTING MATERIALS: