Legislation Details

File #: 22-0083    Name: 22-03 McK Engineering
Type: Agenda Item Status: Public Hearing
In control: McKinney Community Development Corporation
On agenda: 1/27/2022 Final action:
Title: Conduct a Public Hearing and Consider/Discuss/Act on a Project Grant Application Submitted by City of McKinney, Engineering Department (#22-03) in the Amount of Four Hundred Thousand and NO/100 ($400,000.00) for the Expansion of Eldorado Parkway from a Four-Lane Divided Roadway to a Six-Lane Divided Roadway in Accordance with the City of McKinney Master Thoroughfare Plan to Support the Anticipated Traffic Which Will Be Generated by the H-E-B Development. Amount Requested Represents 36% of Total Project Cost.
Attachments: 1. Application Packet, 2. Presentation

Title

Conduct a Public Hearing and Consider/Discuss/Act on a Project Grant Application Submitted by City of McKinney, Engineering Department (#22-03) in the Amount of Four Hundred Thousand and NO/100 ($400,000.00) for the Expansion of Eldorado Parkway from a Four-Lane Divided Roadway to a Six-Lane Divided Roadway in Accordance with the City of McKinney Master Thoroughfare Plan to Support the Anticipated Traffic Which Will Be Generated by the H-E-B Development. Amount Requested Represents 36% of Total Project Cost.

Summary

COUNCIL GOAL:                     Direction for Strategic and Economic Growth

(1A): Establish regional and infrastructure incentives to increase economic growth

(1D): Leverage the existing partnerships with MEDC and MCDC

 

MEETING DATE:                     January 27, 2022

DEPARTMENT:                      McKinney Community Development Corporation

CONTACT:                       Cindy Schneible, President

ITEM SUMMARY: 

•                     The McKinney Community Development Corporation will conduct a public hearing on the project grant application submitted by The City of McKinney, Engineering Department in the amount of $400,000 for the Expansion of Eldorado Parkway from a Four-Lane Divided Roadway to a Six-Lane Divided Roadway in Accordance with the City of McKinney Master Thoroughfare Plan to Support the Anticipated Traffic Which Will Be Generated by the H-E-B Development.

•                     This expansion is consistent with the City of McKinney Master Thoroughfare Plan.

•                     Expansion will be funded through a combination of roadway impact fees, funds from CIP Project ST1838 ($700,000), and MCDC ($400,000) ST1838.

•                     Design for this project is underway and expected completion of construction is Spring 2023.

•                     Job creation for the development is estimated at 250-350.

BACKGROUND INFORMATION:  

•                     The City of McKinney’s Engineering Department is responsible for the review and approval of all new public improvement construction and reconstruction projects with the City limits and the ETJ.

•                     This project expansion is consistent with the City of McKinney Master Thoroughfare Plan.

•                     Infrastructure assistance to retail or commercial projects is an eligible Type B project.

 

FINANCIAL SUMMARY:

•                     Funds allocated for FY22 for discretionary Project Grants is $1,749,025, with an additional $6,000,000 for economic development projects.

•                     The request is eligible for MCDC consideration under Section 501.103 of the Texas Local Government Code.

 

SUPPORTING MATERIALS:

•                     Application Packet

•                     Presentation