File #: 23-0616    Name: ST2226 FY22 Street Repairs Change Order
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 8/1/2023 Final action: 8/1/2023
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Change Order with Cam-Crete Contracting, Inc., for the Construction of the FY22 Street Repairs Project
Attachments: 1. Resolution

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Change Order with Cam-Crete Contracting, Inc., for the Construction of the FY22 Street Repairs Project

 

Summary

 

COUNCIL GOAL:                     Operational Excellence

                     (2B: Balance available resources to accommodate the growth and maintenance needs of the city)

 

MEETING DATE:                     August 1, 2023

 

DEPARTMENT:                     Development Services / Engineering

 

CONTACT:                     Blake Sills, PE, Engineering CIP Manager

                     Brook Retta, PE, CIP Engineer

 

RECOMMENDED CITY COUNCIL ACTION:

                     Approval of Resolution

 

ITEM SUMMARY:

                     This Resolution authorizes the City Manager to execute a change order with Cam-Crete Contracting, Inc., for the Construction of the FY22 Street Repairs Project (CIP Project ST2226) for an increase in the not to exceed fee from $3,200,000 to a total aggregate contract amount, inclusive of any additional supplemental agreements, not to exceed $3,375,000.

 

BACKGROUND INFORMATION: 

                     Cam-Crete Contracting, Inc. is currently under contract with the City for the Construction of the FY22 Street Repairs Project (CIP Project ST2226). Their contract includes the following major construction elements:

o                     Street concrete panel removal/replacement

o                     Residential alley reconstruction

                     As construction has progressed, the following additional services have been requested from the City Engineering Department which were not included in the original contract:

o                     Alley reconstruction along Redondo Drive, which includes widening one alley from 8’ to 9’.                     

o                     Pavement and sidewalk reconstruction along Heritage Drive.

o                     Alley reconstruction along Gwendola Drive.

o                     Additional miscellaneous concrete pavement reconstruction to ensure proper storm water drainage flow.

                     Below are change orders for these additional services in the combined amount of $506,702.11 resulting in the total aggregate contract amount of $3,344,730.86. This amount is 17.85% over the original contract amount of $2,838,028.75 and exceeds the previously authorized not to exceed amount of $3,200,000:

o                     Change order 1 in the amount of $63,117.99 was executed on November 21, 2022.

o                     Change order 2 in the amount of $443,584.12 is pending execution with the approval of this item.

                     With approval of this change order, project construction is anticipated to be completed September 2023.

 

FINANCIAL SUMMARY:

                     This Resolution authorizes a contract and all necessary change orders with Cam-Crete Contracting, Inc., for an amount not to exceed $3,375,000.

                     With the approval of this item, $0 will remain in Project ST2226.

 

BOARD OR COMMISSION RECOMMENDATION:

                     N/A