Legislation Details

File #: 16-989    Name: Community Center A/E Additional Service #2
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 10/4/2016 Final action: 10/4/2016
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute Contract Amendments to the Professional Services Contract with Architects Phelps/Wood of Frisco, Texas, for Architectural and Engineering (A/E) Services Related to the Design and Construction of the Community Center Patio Project
Attachments: 1. Resolution

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute Contract Amendments to the Professional Services Contract with Architects Phelps/Wood of Frisco, Texas, for Architectural and Engineering (A/E) Services Related to the Design and Construction of the Community Center Patio Project

 

Summary

 

COUNCIL GOAL:                     Enhance the Quality of Life in McKinney

 

MEETING DATE:                     October 4, 2016

 

DEPARTMENT:                      Parks and Recreation / Public Works

 

CONTACT:                       Rhoda L. Savage - Director of Parks and Recreation

                     Patricia L. Jackson, PE - Facilities Construction Manager

 

 

RECOMMENDED CITY COUNCIL ACTION:                     

•                     Approval of the Resolution.

 

ITEM SUMMARY: 

•                     This Resolution authorizes a contract amendment with Architects Phelps/Wood related to the design and construction of the Community Center Patio project for an additional $12,500 and total amount not to exceed $72,400.

 

BACKGROUND INFORMATION: 

•                     On April 15, 2014, a professional services contract was authorized to provide architectural and engineering services related to the design and construction of the Community Center patio for a not to exceed amount of $60,000.  This amount included basic services valued at $55,000 and a design contingency of $5,000.

•                     The project bid in April 2015, with only one bid being submitted.

•                     The bid was over budget, the bid was rejected, and staff assessed the feasibility of project rebidding.

•                     Additional funds for the project were approved in the FY 15-16 Budget.

•                     Additional funds were added as needed to cover additional design fees as well as construction.

•                     In order to expend the funds designated for the additional design services, a contract amendment to the professional services contract is needed.

•                     The contract amendment would add $12,400 to the design contract and increase the not to exceed amount to $72,400.

•                     The project rebid on May 3, 2016, with three bids being submitted.

•                     City Council approved the bid award for Drive Construction and the project is currently under construction.

 

FINANCIAL SUMMARY: 

•                     The Resolution authorizes the City Manager to execute a contract amendment to the existing professional design services contract with Architects Phelps/Wood for an amount not to exceed $72,400.

•                     The Community Center patio project (PK4252) was fully funded in the FY15-16 Capital Improvements Program with a funding source of previously issued bonds and MCDC sales tax revenues.

                     

BOARD OR COMMISSION RECOMMENDATION:

•                     N/A