Legislation Details

File #: 21-0648    Name: FC2058 - Crossland - GMP Amendment
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 7/20/2021 Final action: 7/20/2021
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract Amendment to the Construction Manager at Risk (CMAR) Contract with Crossland Construction Company, Inc. (Crossland) whose local office is in Prosper, Texas for a Guaranteed Maximum Price (GMP) Related to the Construction Remodel of the North Public Works Complex Project (FC2058) Located at 3501 North Central Expressway, McKinney
Attachments: 1. Resolution, 2. GMP Proposal, 3. Value Management Log

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract Amendment to the Construction Manager at Risk (CMAR) Contract with Crossland Construction Company, Inc. (Crossland) whose local office is in Prosper, Texas for a Guaranteed Maximum Price (GMP) Related to the Construction Remodel of the North Public Works Complex Project (FC2058) Located at 3501 North Central Expressway, McKinney

 

Summary

 

COUNCIL GOAL:                     Operational Excellence

                     (2B: Balance Available Resources to Accommodate the Growth

                     and Maintenance Needs of the City)

 

MEETING DATE:                     July 20, 2021

 

DEPARTMENT:                      Public Works

 

CONTACT:                     Patricia L. Jackson, PE, Facilities Construction Manager

 

RECOMMENDED CITY COUNCIL ACTION:                     

•                     Approval of the Resolution.

 

ITEM SUMMARY: 

•                     This Resolution establishes a Guaranteed Maximum Price (GMP) of $8,749,801 as proposed by Crossland Construction Company, Inc. 

•                     This Resolution authorizes the City Manager to execute a contract amendment with Crossland Construction Company, Inc., the Construction Manager at Risk for the North Public Works Complex Project.

 

BACKGROUND INFORMATION: 

•                     The construction documents were issued on April 30, 2021 and have been advertised for bids by Crossland Construction Company, Inc.

•                     Crossland has compiled the bids and submitted a final Guaranteed Maximum Price for approval.

•                     With this approval, Crossland will be notified to begin construction with completion scheduled for June 2022.

•                     Crossland Construction Company, Inc. is ranked among the top general contractors in North Texas and the nation. They are a Prosper, Texas based firm and have successfully completed multiple projects for McKinney and many other municipalities.

 

FINANCIAL SUMMARY: 

•                     The Resolution authorizes the City Manager to execute a contract amendment to the existing Construction Manager at Risk (CMAR) services contract, for construction services with Crossland Construction Company, Inc. for an amount not to exceed $8,749,801.

•                     A companion budget amendment being presented will amend the Fiscal Year 2020-2021 Annual Budget and the 2021-2025 Capital Improvement Program to provide $1,250,000 additional funding for the North Public Works Complex Project (FC2058).

•                     With approval of this item and the companion agenda item, the total project budget remaining in project FC2058 will be $515,646.

 

BOARD OR COMMISSION RECOMMENDATION: