File #: 24-1205    Name: WW2338 - Joplin Dr. Sewer Imp - Design SA#1
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 2/6/2024 Final action: 2/6/2024
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Supplemental Agreement with Gresham Smith for Professional Engineering Design Services for the Joplin Drive Sewer Improvements Project
Attachments: 1. Resolution, 2. Location Map

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Supplemental Agreement with Gresham Smith for Professional Engineering Design Services for the Joplin Drive Sewer Improvements Project

 

Summary

 

COUNCIL GOAL:                     Direction for Strategic and Economic Growth

                     (1A: Establish regional and infrastructure incentives to increase economic growth)

 

MEETING DATE:                     February 06, 2024

 

DEPARTMENT:                     Development Services / Engineering

 

CONTACT:                     Katie McCarty, P.E., Engineering CIP Manager

                     Manjeeta Sitaula, P.E., CIP Engineer

 

 

RECOMMENDED CITY COUNCIL ACTION:

                     Approval of Resolution.

 

ITEM SUMMARY:

                     This Resolution authorizes a supplemental agreement with Gresham Smith to provide additional professional engineering services for the design of the Joplin Drive Sewer Improvements Project (WW2338) for an increase in the not to exceed from $93,593 to a total aggregate contract amount, inclusive of any additional supplemental agreements, not to exceed $120,000.

 

BACKGROUND INFORMATION:

                     Gresham Smith is currently under contract with the City for design services related to the Joplin Drive Sewer Improvements Project. As design on the project has progressed, the following additional services will be required which were not included in Gresham Smith’s original contract:

o                     Prepare easement acquisition field notes for six (6) parcels of permanent sanitary sewer and temporary construction easements.

                     Design of the project began in March 2023 and is expected to be completed by April 2024.

                     Gresham Smith submitted a proposal for $16,500 for these additional services ($110,093 aggregate contract total), which has been reviewed by staff and exceeds the previously authorized not to exceed amount of $93,593.

 

FINANCIAL SUMMARY:

                     This Resolution authorizes a supplemental agreement with Gresham Smith for an increase in the not to exceed contract amount from $93,593 to a total aggregate contract amount, inclusive of any additional supplemental agreements, not to exceed $120,000.

                     Funding for this contract is included in the Capital Improvements Program (WW2338).

                     With approval of this item, $210,089.11 will remain in project WW2338.

 

BOARD OR COMMISSION RECOMMENDATION:

                     N/A