File #: 24-1770    Name: ST2222, DR2222, WA2222, WW2222 Design Supplemental
Type: Resolution Status: Consent Item
In control: City Council Regular Meeting
On agenda: 7/16/2024 Final action:
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Supplemental Agreement with Grantham & Associates, Inc. for Professional Engineering Design Services for the College, Hunt, Davis & Church Street Infrastructure Improvements Project and Any Necessary Supplemental Agreements
Attachments: 1. Resolution, 2. Location Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Supplemental Agreement with Grantham & Associates, Inc. for Professional Engineering Design Services for the College, Hunt, Davis & Church Street Infrastructure Improvements Project and Any Necessary Supplemental Agreements

 

Summary

 

COUNCIL GOAL:                     Operational Excellence

                     (2B: Balance available resources to accommodate the growth and maintenance needs of the city)

 

MEETING DATE:                     July 16, 2024

 

DEPARTMENT:                        Development Services / Engineering                     

 

CONTACT:                       Blake Sills, PE, CIP Manager

                     Brook Retta, PE, CIP Project Manager

 

RECOMMENDED CITY COUNCIL ACTION:                     

                     Approval of Resolution.

 

ITEM SUMMARY: 

                     This Resolution authorizes the City Manager to execute a supplemental agreement with Grantham & Associates, Inc. for additional professional consulting engineering services for the College, Hunt, Davis & Church Street Infrastructure Improvements Project (CIP Projects ST2222, DR2222, WA2222, and WW2222) for an increase in the not to exceed from $790,000 to a total aggregate contract amount, inclusive of any additional supplemental agreements, not to exceed $900,000.

 

BACKGROUND INFORMATION: 

                     Grantham & Associates, Inc. is currently under contract with the City for professional consulting engineering services related to the College, Hunt, Davis & Church Street Infrastructure Improvements Project (CIP Projects ST2222, DR2222, WA2222, and WW2222).

                     The project consists of improvements to underground water and wastewater, street pavement rehabilitation, pedestrian walkways/ADA accessibility, landscaping, stormwater improvements, and other associated street elements for the following streets:

o                     Hunt Street between College Street and Kentucky Street

o                     Davis Street between College Street and SH 5 (excluding Church Street to Kentucky Street which includes planned drainage improvements under CIP projects ST2213, DR2213, WA2213, and WW2213)

o                     Church Street between Hunt Street and Davis Street

o                     College Street between Lamar Street and Willie Street

                     As detailed design have progressed, the following additional services have/will be required which were not included in the original contract:

o                     Expanded survey, subsurface utility engineering, and design for stormwater improvements from Virginia Street to Davis Street east of College Street.

o                     Additional property owner and franchise utility coordination associated to the stormwater improvements.

                     Construction of the project is expected to begin towards the end of 2024.

                     Grantham & Associates, Inc. submitted a proposal for $89,705.00 for the remaining additional services ($858,815.00 aggregate contract total), which has been reviewed by staff and exceeds the previously authorized not to exceed amount of $790,000.

 

FINANCIAL SUMMARY: 

                     The Resolution authorizes a supplemental agreement with Grantham & Associates, Inc. for an increase in the not to exceed contract amount from $790,000 to a total aggregate contract amount, inclusive of any additional supplemental agreements, not to exceed $900,000.

                     Funding for this contract is included in the Capital Improvements Program (ST2222, DR2222, WA2222, and WW2222).

o                     Project ST2222 - Account 21 - $465,500.00.

o                     Project DR2222 - Account 62 - $0.00.

o                     Project WA2222 - Account 20 - $295,000.00.

o                     Project WW2222 - Account 20 - $139,500.00.

                     With the approval of this item, $5,034,500.00 will remain in Project ST2222.

                     With the approval of this item, $696,250.00 will remain in Project DR2222.

                     With the approval of this item, $2,735,300.00 will remain in Project WA2222.

                     With the approval of this item, $1,830,200.00 will remain in Project WW2222.

 

BOARD OR COMMISSION RECOMMENDATION:

                     N/A