File #: 24-1124    Name: East Louisiana Street and Railroad Improvements Construction Contract
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 1/16/2024 Final action: 1/16/2024
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Enter into a Construction and Maintenance Agreement with Dallas Garland & Northeastern Railroad Inc. (DGNO), for the Railroad Crossing Improvements at East Louisiana Street Required for the East Louisiana Street Improvements Project
Attachments: 1. Resolution, 2. Location Map

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Enter into a  Construction and Maintenance Agreement with Dallas Garland & Northeastern Railroad Inc. (DGNO), for the Railroad Crossing Improvements at East Louisiana Street Required for the East Louisiana Street Improvements Project

 

Summary

 

COUNCIL GOAL:                     Direction for Strategic & Economic Growth

                     (1A: Establish regional and infrastructure incentives to increase economic growth)

 

                     Operational Excellence

                     (2B: Balance available resources to accommodate the growth and maintenance needs of the city)

 

MEETING DATE:                     January 16, 2024

 

DEPARTMENT:                     Development Services / Engineering

 

CONTACT:                     Blake Sills, PE, Engineering CIP Manager

                     Aniswarie Kanamazina, PE, CIP Engineer

 

RECOMMENDED CITY COUNCIL ACTION:

                     Approval of Resolution

 

ITEM SUMMARY:

                     This Resolution authorizes the City Manager to enter into a Construction and Maintenance Agreement with Dallas Garland & Northeastern Railroad Inc. (DGNO), for the railroad crossing improvements at East Louisiana Street required for the East Louisiana Street Improvements Projects (ST1817) for a total contract amount not to exceed $519,117.

 

BACKGROUND INFORMATION:

                     The East Louisiana Street Improvements Project is currently under construction.

                     Improvements to the railroad facilities, including a new roadway crossing and automated warning devices with the addition of roadway gates are proposed to be constructed in conjunction with the roadway improvements.

                     The railroad is operated by the Dallas Garland & Northeastern Railroad (DGNO) who maintain the railroad facilities within Dallas Area Rapid Transit’s (DART) property. DGNO utilizes specialized contractors to carry out any maintenance work or improvements to these facilities.

                     DGNO and its contractors will construct the proposed improvements and City will reimburse DGNO for the total project cost associated with the railroad crossing at  East Louisiana Street.

FINANCIAL SUMMARY:

                     This Resolution authorizes a contract and all necessary change orders with Dallas Garland & Northeastern Railroad Inc. (DGNO), for an amount not to exceed $519,117.

                     With the approval of this item $480,167.99 will remain in Project ST1817.

 

BOARD OR COMMISSION RECOMMENDATION:

                     N/A