Legislation Details

File #: 21-0823    Name: Finch Park Phase V
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 9/21/2021 Final action: 9/21/2021
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract and All Necessary Change Orders with J.C. Commercial, Inc of Lewisville, Texas, for the Construction of the Finch Park Phase V Improvement Project (PK2039)
Attachments: 1. Resolution, 2. Bid Tabulation

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract and All Necessary Change Orders with J.C. Commercial, Inc of Lewisville, Texas, for the Construction of the Finch Park Phase V Improvement Project (PK2039)

 

Summary

 

COUNCIL GOAL:                     Enhance the Quality of Life in McKinney                                                               

(5A: Create affordable recreational and cultural arts activities for all ages throughout the city)

(5C: Continue to market and highlight McKinney as a unique destination for residents and visitors alike)

(5E: Develop sustainable quality of life improvements within the City of McKinney)

 

 

MEETING DATE:                     September 21, 2021

 

DEPARTMENT:                      Parks and Recreation

 

CONTACT:                                            Michael Kowski, Director of Parks and Recreation

 

RECOMMENDED CITY COUNCIL ACTION:                     

•                     Approval of the Resolution.

 

ITEM SUMMARY: 

•                     This Resolution authorizes the City Manager to execute a contract and all necessary change orders with J.C. Commercial, Inc. of Lewisville, Texas for the Construction of Finch Park Phase V Improvement Project (PK2039) for at total contract amount not to exceed $2,538,974.33.

 

BACKGROUND INFORMATION: 

•                     City staff worked with JBI Partners, Inc. on preparing the construction plans and specifications as needed for project bidding.

 

•                     The Finch Park Phase V improvements will include a new expanded playground and splash pad area with centralized pavilion, additional trails, entry signage, improved flat work and new landscaping.

 

•                     The project was bid with 3 possible add alternates.

o                     Alternate 1: Pickle ball court

o                     Alternate 2: Fitness Court

o                     Alternate 3: Bocce ball court

 

•                     The City issued invitations to bid (21-66CC) to solicit responses from qualified contractors for construction of Finch Park Phase V, Improvements.

o                     Advertised in the McKinney Courier Gazette

o                     Posted on McKinney TV

o                     1,066 matching eBid Supplier Notifications

o                     Including 45 HUB supplier notifications

 

•                     In response to all notices published, four (4) bids were received on September 9, 2021 from:

o                     DL Meacham Construction

o                     J.C. Commercial, Inc.

o                     Mart, Inc.

o                     RLM EarthCO Inc.

 

•                     J.C. Commercial, Inc. submitted the low bid in the amount of 2,388,974.33 for Base Bid plus Add Alternate 1, pickle ball court.

 

•                     Staff, along with JBI Partners, Inc. support and recommend awarding the construction bid to J.C. Commercial, Inc. in an amount of $2,388,974.33 along with a $150,000 contingency for a total not to exceed amount of $2,538,974.33. (Includes base bid + add alternate 1 + contingency)  

 

•                     Upon approval, construction should begin in October 2021 with a 204-day contract schedule.

 

FINANCIAL SUMMARY: 

•                     The Finch Park Phase V Improvement Project (PK2039) is a FY21-22 Capital Improvements Program funded by MCDC funds and bond monies.

 

•                     Below is a breakdown showing the expected project cost of $2,793,378.25:

                                                         

o                     Architectural and Engineering Design Fees                            $   149,000.00

o                     Construction Contract                                                                                          $2,388,974.33

o                     Construction Contract Contingency                          $                      150,000.00

o                     Materials Testing                                                       $     60,000.00

o                     Project Contingency                                                                                                                $     45,403.92

                      Total                                                                                             $2,793,378.25

 

•                     Upon approval of this item, $254,403.92 remains in the project budget.

 

BOARD OR COMMISSION RECOMMENDATION:

•                     On September 9th, 2021, the Parks, Recreation and Open Space Advisory Board recommended to City Council the award of the construction contract.