Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Garver, LLC for Professional Engineering Design Services for the Residential Infrastructure Improvements (Anthony, Gough, Neilson, Miller & Enloe) Project and Authorizing Any Necessary Supplemental Agreements
Attachments: 1. Resolution, 2. Location Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Garver, LLC for Professional Engineering Design Services for the Residential Infrastructure Improvements (Anthony, Gough, Neilson, Miller & Enloe) Project and Authorizing Any Necessary Supplemental Agreements

Summary

COUNCIL GOAL: Operational Excellence
(2B: Balance available resources to accommodate the growth and maintenance needs of the city)

MEETING DATE: July 7, 2026

DEPARTMENT: Development Services / Engineering

CONTACT: Blake Sills, PE, Engineering CIP Manager
Josh McNeil, PE, CIP Engineer II

RECOMMENDED CITY COUNCIL ACTION:
* Approval of Resolution.

ITEM SUMMARY:
* This Resolution authorizes the City Manager to execute a contract in the amount of $1,033,280, as well as all required supplemental agreements thereto, with Garver, LLC for professional consulting engineering services for the Residential Infrastructure Improvements (Anthony, Gough, Neilson, Miller & Enloe) Project (CO2511) for a total aggregate contract amount, inclusive of any supplemental agreements, not to exceed $1,140,000.

BACKGROUND INFORMATION:
* The FY26-30 Capital Improvement Program (CIP) includes funding for comprehensive infrastructure improvements to the following street segments in the Mouzon Neighborhood in East McKinney.
o Anthony Street from Evelyn Street to Enloe Road
o Gough Street from Wilson Street to Anthony Street
o Neilson Street from Anthony Street to Greenville Road
o Miller Street from Anthony Street to Greenville Road
o Enloe Road from Greenville Road to Airport Drive
* Improvements in this project's scope of work include approximately 13,000 square yards of concrete street paving, 2,500 linear feet of proposed storm lines ranging in size from 24 inch to 60 inch, 6,300 linear feet of sanitary sewer lines, and 5,500 linear feet of water line.
* Garver, LLC submitted a response to 24-46RFQ for Utility Professionals Services and was one of fourteen (14) firms...