Title: Consider/Discuss/Act on an Ordinance Amending the Fiscal Year 2022-2023 Annual Budget to Provide Funds for the purpose of the TUPPS Brewer Project (4B2009)
Attachments: 1. Ordinance

Title

Consider/Discuss/Act on an Ordinance Amending the Fiscal Year 2022-2023 Annual Budget to Provide Funds for the purpose of the TUPPS Brewer Project (4B2009)

 

Summary

 

COUNCIL GOAL:                     Direction for Strategic & Economic Growth

 

MEETING DATE:                     April 4, 2023

 

DEPARTMENT:                      McKinney Community Development Corporation

 

CONTACT:                       Cindy Schneible, MCDC President

 

 

RECOMMENDED CITY COUNCIL ACTION:                     

•                     Approval of the ordinance.

 

ITEM SUMMARY: 

•                     This Ordinance will amend the Fiscal Year 2022-2023 Annual Budget of the McKinney Community Development Corporation to provide additional funds for the TUPPS Brewer Project (4B2009).

 

BACKGROUND INFORMATION: 

•                     MCDC Project #20-09, TUPPS Brewery Expansion Project, was approved by the McKinney Community Development Corporation on June 25, 2020 and by the McKinney City Council on July 7, 2020.

•                     Additional funding, from MCDC, in the amount of $2,000,000 was approved following a public hearing conducted during a joint meeting with McKinney City Council on December 7, 2021.

•                     City Council approved funding in the amount of $2,500,000 at the joint meeting with MCDC on December 7, 2021.

•                     MCDC board approved a 10-year loan, in the amount of $750,000, to the project at the meeting held January 26, 2023, contingent upon receipt of $150,000 from TUPPS. The interest rate on the loan is 4.33%. Interest only payments to be made in the year on.

 

 

FINANCIAL SUMMARY: 

•                     Additional funding in the amount of $150,000 was provided by TUPPS and will be appropriated in the MCDC budget for the TUPPS Brewery expansion project.

•                     Total funding for project #20-09:

o                     MCDC - $14,083,262 (including $750,000 loan)

o                     Tupps - $1,400,000

o                     City - $2,500,000

o                     Total $17,983,262

•                     Additional investment by MCDC was made for the acquisition of a 4.3-acre tract of land for the project in the amount of $2,648.493.

 

BOARD OR COMMISSION RECOMMENDATION:

•                     MCDC Board recommends approval.