File #: 19-0652    Name: Airport Runway Environmental Assessment
Type: Ordinance Status: Approved
In control: City Council Regular Meeting
On agenda: 8/5/2019 Final action: 8/5/2019
Title: Consider/Discuss/Act on an Ordinance Amending the Fiscal Year 2018-2019 Annual Budget and the 2019-2023 Capital Improvements Program to Provide Funds for Environmental Assessment for Project AI2035, Extend Runway-Environmental Documentation
Attachments: 1. Ordinance

Title

Consider/Discuss/Act on an Ordinance Amending the Fiscal Year 2018-2019 Annual Budget and the 2019-2023 Capital Improvements Program to Provide Funds for Environmental Assessment for Project AI2035, Extend Runway-Environmental Documentation

 

Summary

 

COUNCIL GOAL:                     Maximize the Development Potential of McKinney National Airport (3A:  Implement initiatives and strategies, including public-private partnerships, to attract and expand corporate and commercial aviation)

 

 

MEETING DATE:                     August 5, 2019

 

DEPARTMENT:                      Airport

 

CONTACT:                       Kenneth Carley, A.A.E., Airport Director

 

 

RECOMMENDED CITY COUNCIL ACTION:                     

                     Approve Ordinance

 

ITEM SUMMARY: 

                     This Ordinance amends the Fiscal Year 2018-2019 Annual Budget and the 2019-2023 Capital Improvements Program by transferring $750,000 from the Airport Operating Fund balance to the Airport Construction Fund and appropriating the funds into Project AI2035, Extend Runway-Environmental Documentation, for an Environmental Assessment to support planning and preliminary design for a future runway extension project. TxDOT Aviation Division will manage the Environmental Assessment on behalf of the Airport.

 

BACKGROUND INFORMATION: 

                     The Airport Master Plan recommends extending Runway 18/36 approximately 1,500 feet to accommodate future growth. It is necessary to accomplish an Environmental Assessment to understand the potential impacts of the runway extension and to develop a preferred alternative.

 

FINANCIAL SUMMARY: 

                     This Ordinance amends the Fiscal Year 2018-2019 Annual Budget and the 2019-2023 Capital Improvements Program by transferring $750,000 from the Airport Operating Fund balance to the Airport Construction Fund and appropriating the funds into Project AI2035, Extend Runway-Environmental Documentation, for an Environmental Assessment.

                     Total Project costs are estimated not to exceed $750,000. The City will be responsible for 100% of the total project costs.

 

BOARD OR COMMISSION RECOMMENDATION:

                     N/A