Title
Update on the Eldorado & Virginia Parkway Panel Replacement Project
Summary
COUNCIL GOAL: OPERATIONAL EXCELLENCE
(2.1: Balance available resources to accommodate the growth and maintenance needs of the city.)
MEETING DATE: May 5, 2026
DEPARTMENT: Public Works
CONTACT: Katie McKenzie, PE, Assistant Director of Public Works
Ryan Gillingham, PE, Director of Public Works
RECOMMENDED CITY COUNCIL ACTION:
• N/A
ITEM SUMMARY:
• Status update for the Eldorado & Virginia Parkway Panel Replacement project.
BACKGROUND INFORMATION:
• Contract with Garret Shields Infrastructure, LLC was executed in January 2025.
• Construction on Eldorado Parkway is complete.
• Contract amount will limit the construction along Virginia Parkway.
FINANCIAL SUMMARY:
• N/A
BOARD OR COMMISSION RECOMMENDATION:
• N/A