File #: 24-1664    Name: ALCMS Installation Project
Type: Resolution Status: Consent Item
In control: City Council Regular Meeting
On agenda: 6/18/2024 Final action:
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract and All Necessary Change Orders with Vellutini Corporation dba Royal Electric Company for the Airfield Lighting Control and Monitoring System (ALCMS) Installation Project
Attachments: 1. Resolution, 2. Recommendation of Award_Unit Bid Tab
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract and All Necessary Change Orders with Vellutini Corporation dba Royal Electric Company for the Airfield Lighting Control and Monitoring System (ALCMS) Installation Project

Summary

COUNCIL GOAL: Operational Excellence
(2A: Balance available resources to accommodate the growth and maintenance needs of the city)

MEETING DATE: June 18, 2024

DEPARTMENT: McKinney National Airport
Procurement Services

CONTACT: Kenneth Carley, Director of Airport
Erika Roberts, Buyer II

RECOMMENDED CITY COUNCIL ACTION:
* Approval of Resolution

ITEM SUMMARY:
* This Resolution authorizes the City Manager to execute a contract and all necessary change orders with Vellutini Corporation dba Royal Electric Company for the Construction of ACLMS Installation project for a total contract amount not to exceed $294,000.00
* This is part of project Al2452, ACLMS installation project.

BACKGROUND INFORMATION:
* Garver, LLC prepared the construction plans for the ALCMS installation project.
* The City issued an Invitation to Bid (24-55CC) to solicit responses from qualified contractors for the ALCMS Installation on May 12, 2024.
o Advertised in McKinney Courier Gazette and Celina Record
o Posted on McKinney TV
o 87 matching eBid supplier notifications which included 6 Historically Underutilized Business (HUB) suppliers.
* Out of the 87 matching supplier notifications, three (3) bids were received and opened by Procurement Services on June 6, 2024. The following Is a summary of the bids:

Bid No.
Bidder
Bid Amount|1010|BC Company
$325,424.00|1010|F&W Electrical Contractors, Inc.
$399,900.00|1010|Velluntini Corporation dba Royal Electric Company
$294,000.00

* Velluntini Corporation dba Royal Electric Company submitted references and qualifications that were evaluated in accordance with the bid specifications as noted in the attached Letter or Recommendation from Garver, LLC dated June 10, 2...

Click here for full text