File #: 25-2850    Name: WA2240 Budget Ordinance
Type: Ordinance Status: Regular Agenda Item
In control: City Council Regular Meeting
On agenda: 6/3/2025 Final action:
Title: Consider/Discuss/Act on an Ordinance Amending the Fiscal Year 2024-2025 Annual Budget and Amending the 2025-2029 Capital Improvements Program to Provide Funds for the Chestnut 0.5 MG Elevated Storage Tank Rehabilitation Project (WA2240)
Attachments: 1. Ordinance, 2. Location Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Consider/Discuss/Act on an Ordinance Amending the Fiscal Year 2024-2025 Annual Budget and Amending the 2025-2029 Capital Improvements Program to Provide Funds for the Chestnut 0.5 MG Elevated Storage Tank Rehabilitation Project (WA2240)
Summary

COUNCIL GOAL: Operational Excellence
(2B: Balance available resources to accommodate the growth and maintenance needs of the city)
MEETING DATE: June 3, 2025
DEPARTMENT: Development Services / Engineering
CONTACT: Blake Sills, PE, Engineering CIP Manager
Paul Tucker, PE, Senior Utility Engineer

RECOMMENDED CITY COUNCIL ACTION:
* Approve ordinance

ITEM SUMMARY:
* This Ordinance amends the Fiscal Year 2024-2025 Annual Budget and Amending the 2025-2029 Capital Improvement Program to provide funding for the Chestnut 0.5 MG Elevated Storage Tank Rehabilitation Project (CIP Project WA2240)

BACKGROUND INFORMATION:

* Blastco Texas Inc. for the Chestnut 0.5 MG Elevated Storage Tank Rehabilitation Project (CIP Project WA2240).
* Current funding/revenues in CIP Project WA2240 are insufficient to cover the actual construction costs of the project and associated construction contingencies based on significant construction price inflation that has occurred over the life of the project.
* A budget amendment is needed to increase the project budget to cover the actual construction cost of the project and advance the needed Chestnut 0.5 MG Elevated Storage Tank Rehabilitation Project depending on the option selected.
o Option 1 - Full Contract
o Option 2 - Removal of Leg Column RBGW Lighting ($210,000 reduction)
o Option 3 - Removal of Leg Column RBGW Lighting, Site work, landscaping, and irrigation ($613,165 reduction)
* A table depicting the funding for each option is summarized in the table below.
Funding Sources
Option 1 - Bid Total plus NTE
$4,500,000
Option 2 - Reduced Bid Total plus NTE
$4,275,000
Option 3- Reduced Bid Total plus NTE
$3,689,000
Fund 20
$3,265,000
$3,265,000
$3,265,000
MCDC Grant
$500,000
$500,000
$...

Click here for full text