Legislation Details

File #: 26-0457    Name: RES - Airport Taxiway A Phase II
Type: Resolution Status: Regular Agenda Item
In control: City Council Regular Meeting
On agenda: 5/19/2026 Final action:
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to execute a Contract with Mario Sinacola & Sons Excavating, Inc. for construction of the Mckinney National Airport Taxiway A Phase II Project (AI2633) and authorizing all necessary change orders under said contract up to the aggregate contract amount, inclusive of any change orders
Attachments: 1. Resolution, 2. Recommendation of Award Letter, 3. Form 1295, 4. Presentation
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to execute a Contract with Mario Sinacola & Sons Excavating, Inc. for construction of the Mckinney National Airport Taxiway A Phase II Project (AI2633) and authorizing all necessary change orders under said contract up to the aggregate contract amount, inclusive of any change orders

Summary

COUNCIL GOAL:
Maximize the Development Potential of McKinney National Airport
* 3.1: Implement initiatives and strategies, including public-private partnerships, to attract and expand corporate and commercial aviation including the viability of passenger service.

* 3.2: Identify and implement land use regulations and policies which preserve and expand long-term operational excellence.

MEETING DATE: May 19, 2026

DEPARTMENT: Airport

CONTACT: Kenneth Carley, A.A.E., Airport Director


RECOMMENDED CITY COUNCIL ACTION:
* Approve Resolution

ITEM SUMMARY:
* This resolution authorizes the City Manager to execute a contract in the amount of $6,948,170.10 with Mario Sinacola & Sons Excavating, Inc. for the construction of the Taxiway A Phase II project, and authorizing all necessary change orders under said contract up to the aggregate amount, inclusive of any change orders, not to exceed $7,642,987.11.

BACKGROUND INFORMATION:
* Garver, LLC prepared the construction plans for the Phase II portion of the Taxiway A Rehabilitation.
* On April 3, 2026, Procurement Services issued an Invitation to Bid (26-46ITB) for TKI Taxiway A Rehabilitation Phase II. Out of 408 suppliers notified, three (3) responses were received and opened on April 30, 2026.
* The bids were reviewed by the Airport and Procurement Services. Of the three (3) bids received in response to the solicitation 26-46ITB, the team recommends the award to Mario Sinacola & Sons Excavating, Inc. in the amount of $6,948,170.10.

FINANCIAL SUMMARY:
* This Resolution authorizes a contract in the amount of $6,948,170.10 with Mario Sinacola & Sons ...

Click here for full text