Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Walter P. Moore and Associates, Inc. for Professional Engineering Services for the Wilson Creek Aerial Wastewater Crossing Improvements Project (between S. Hardin Blvd. and McKinney Christian Academy, southwest of Bois D'Arc Road) and Any Necessary Supplemental Agreements
Summary
COUNCIL GOAL: Operational Excellence
(2.1: Balance available resources to accommodate the growth and maintenance needs of the city)
MEETING DATE: October 21, 2025
DEPARTMENT: Development Services / Engineering
CONTACT: Tracy Lund, PE, CIP Assistant Director of Engineering
Melvin Machayo, PE, Senior Utility Engineer
RECOMMENDED CITY COUNCIL ACTION:
* Approval of Resolution.
ITEM SUMMARY:
* This Resolution authorizes the City Manager to execute a contract in the amount of $218,793.00, as well as all required supplemental agreements thereto, with Walter P. Moore and Associates, Inc. for professional engineering services for the Wilson Creek Aerial Wastewater Crossing Improvements Project (between S. Hardin Blvd. and McKinney Christian Academy, southwest of Bois D'Arc Road) (CIP Project CO2429), for a total aggregate contract amount, inclusive of any supplemental agreements, not to exceed $241,000.00.
BACKGROUND INFORMATION:
* The Capital Improvements Program (CIP) includes recurring programmed funding for major repairs and/or replacements of existing water and wastewater mains which have reached the end of their service life and/or have known maintenance concerns.
* CIP Fund 20 and Fund 62 include funding for the Wilson Creek Aerial Wastewater Crossing Improvements Project (between S. Hardin Blvd. and McKinney Christian Academy, southwest of Bois D'Arc Road).
* The project will include replacement of the existing bag wall that is deteriorating, and approximately 240 feet of existing 27" Sanitary sewer aerial crossing over Wilson Creek.
* The project will also consi...