File #: 25-2615    Name: Resolution for Additional Services Agreement for AI2264
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 3/31/2025 Final action: 3/31/2025
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute an Additional Services Agreement with Garver, LLC for McKinney National Airport Project AI2264, East Side Environmental Assessment (EA)
Attachments: 1. Resolution

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute an Additional Services Agreement with Garver, LLC for McKinney National Airport Project AI2264, East Side Environmental Assessment (EA)

 

Summary

 

COUNCIL GOAL:                     Maximize the Development of McKinney National Airport

                     3A: Implement initiatives and strategies, including public-private partnerships, to attract and expand corporate and commercial aviation including the viability of passenger service.

 

                     3B: Identify and implement land use regulations and policies that preserve and expand long-term operational excellence.

 

 

MEETING DATE:                     March 31, 2025

 

DEPARTMENT:                      Airport

 

CONTACT:                       Ken Carley, Airport Director

 

 

RECOMMENDED CITY COUNCIL ACTION:                     

                     Approve Resolution

 

ITEM SUMMARY: 

                     The Resolution authorizes the City Manager to execute an Additional Services Agreement with Garver, LLC for McKinney National Airport Project AI2264, East Side Environmental Assessment (EA).

 

BACKGROUND INFORMATION: 

                     The City has undertaken a planning process which will facilitate future improvements to the McKinney National Airport through the East Side Environmental Assessment in January 2022.

                     The additional services agreement for the Environmental Assessment (EA) is to meet revised EPA and TCEQ Ozone emissions standards implemented in November 2022 through increased air quality modeling.

 

FINANCIAL SUMMARY: 

                     The City of McKinney will be responsible for 100% of the additional project costs of $60,000 increasing the not to exceed amount of the project to $610,000.

                     Upon approval of this item, $0 will remain in AI2264.

 

BOARD OR COMMISSION RECOMMENDATION: