Skip to main content
File #: 10-387    Name: Custer Rd Fire Hydrant Relocations
Type: Resolution Status: Approved and Finalized
In control: City Council Regular Meeting
On agenda: 8/23/2010 Final action: 8/23/2010
Title: Consider/Discuss/Act on a Resolution Authorizing Additional Funding for North Texas Contracting, Inc, to Complete the Custer Road Utility Relocation Project
Attachments: 1. Resolution, 2. Location Map

Title

Consider/Discuss/Act on a Resolution Authorizing Additional Funding for North Texas Contracting, Inc, to Complete the Custer Road Utility Relocation Project

 

Summary

 

MEETING DATE:                     August 23, 2010

 

DEPARTMENT:                                          Development Services/Engineering

 

CONTACT:                                          Jack Carr, PE, Director of Engineering

                                          Paul Tucker, PE, Senior Utility Engineer

                                          Danny Still, PE, CIP Engineer

 

 

RECOMMENDED CITY COUNCIL ACTION:

                     Approval of Resolution.

 

ITEM SUMMARY:

                     This Resolution will authorize additional funding for North Texas Contracting, Inc, to complete the construction of the Custer Road Utility Relocation Project.

 

BACKGROUND INFORMATION:

                     The utility relocation project along Custer Road from Stonebridge Drive to US 380 is nearly complete. 

                     The only substantial work remaining is the relocation of fire hydrants that were installed in locations that conflict with the proposed roadway currently under construction.

                     The total amount required for the hydrant relocations is $35,832.  However, these funds are not being provided by the City. 

                     The design engineer, CP&Y, Inc., and the contractor, North Texas Contracting have both agreed to equally share in the cost necessary to relocate the hydrants to acceptable locations.

                     To facilitate payment to the contractor CP&Y will provide half of the funds, $17,916, to the City. 

                     The City will increase the construction contract with North Texas Contracting by that amount and will pay those funds to the contractor for the work.

 

FINANCIAL SUMMARY:

                     The original contract with North Texas Contracting for this project was approved on June 17, 2008, for an amount not to exceed $6,460,000. 

                     This Resolution will increase that amount by $30,000 to $6,490,000.

                     Funding is available in the Capital Improvements Program in WA3022.

 

BOARD OR COMMISSION RECOMMENDATION:

                     N/A