File #: 26-0071    Name: 4B 26-04 Presidium
Type: Agenda Item Status: Agenda Ready
In control: McKinney Community Development Corporation
On agenda: 1/22/2026 Final action:
Title: Conduct a Public Hearing and Consider/Discuss/Act on a Project Grant Application Submitted by Presidium Group, LLC, (4B26-04) in an Amount of Thirteen Million Six Hundred Thirty-Four Thousand Six Hundred Thirty-Eight Dollars and 49/100 Dollars ($13,634,638.49) for Infrastructure Improvements Related to Development of The Cotton Mill District, Located at 610 Elm Street in McKinney, Texas. Amount Requested Represents 71.3% of Infrastructure Cost for the Project.
Attachments: 1. Application Packet, 2. Presentation
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Conduct a Public Hearing and Consider/Discuss/Act on a Project Grant Application Submitted by Presidium Group, LLC, (4B26-04) in an Amount of Thirteen Million Six Hundred Thirty-Four Thousand Six Hundred Thirty-Eight Dollars and 49/100 Dollars ($13,634,638.49) for Infrastructure Improvements Related to Development of The Cotton Mill District, Located at 610 Elm Street in McKinney, Texas. Amount Requested Represents 71.3% of Infrastructure Cost for the Project.

Summary

COUNCIL GOAL: 1: Direction for strategic and economic growth
1:1 Provide a strong economy by creating a Global Housing Strategy and facilitating a balance between industrial, commercial, residential, and open space.
5: Enhance Quality of Life in McKinney
5.3: Develop sustainable quality of life improvements within the City of McKinney

MEETING DATE: January 22, 2026

DEPARTMENT: McKinney Community Development Corporation

CONTACT: Cindy Schneible, President

ITEM SUMMARY:
* McKinney Community Development Corporation will conduct a public hearing on a project grant application submitted by Presidium Group, LLC, in an amount of $13,634,638.49 for infrastructure improvements related to the construction of The Cotton Mill District. Request is for infrastructure improvements to support Phases 1 through 4 of the overall project.
* Estimated completion for Phase 1 is February 1, 2028. Completion of phases would be within six years.
* Construction of two, three-story office buildings is planned for Phase 3 and 4.
* Based on a report from Catalyst Commercial, the 20-year economic impact of the project is estimated at $826,482,817.
* Presidium owns 8.12 acres with an option for an additional 4.38 acres. Another 15.09 acres is owned by The Cotton Mill.
*
BACKGROUND INFORMATION:
* Presidium is a Texas-based real estate developer, owner, and operator with a 22-year operating history and an existing real estate portfolio with assets totaling $2.6 billion in valuation and co-headquartered in...