Title
Consider/Discuss/Act on a Resolution Authorizing the Formal Rejection of all Proposals under Solicitation 24-23CSP Construction of McKinney Light Walk
Summary
COUNCIL GOAL: Operational Excellence
(2A: Balance available resources to accommodate the growth and maintenance needs of the city)
MEETING DATE: September 17, 2024
DEPARTMENT: Parks Development
Procurement Services
CONTACT: April Butler, Parks Construction Planner II
Mindy Smith, Assistant Procurement Services Manager
RECOMMENDED CITY COUNCIL ACTION:
• Approval of Resolution
ITEM SUMMARY:
• This Resolution authorizes formal rejection of all proposals under Solicitation 24-23CSP Construction of McKinney Light Walk.
BACKGROUND INFORMATION:
• The City issued a Request for Competitive Sealed Proposals (24-23CSP) for the Construction of McKinney Light Walk August 4, 2024.
o Advertised in the McKinney Courier Gazette and Celina Record
o Posted on McKinney TV
o 1087 matching eBid supplier notifications which included 49 Historically Underutilized Business (HUB) suppliers.
• Out of 1087 supplier notifications, one (1) proposal was received and opened by Procurement Services on August 22, 2024. The following is a summary of the proposal:
Bid No. |
Bidder |
Base Bid |
Alternate 1 |
Alternate 2 |
Alternate 3 |
Total Amount Bid |
1 |
Ragle, Inc. |
$5,811,736.72 |
$43,163.85 |
$13,040.00 |
$18,124.93 |
$5,886,065.50 |
• The Engineer’s Opinion of Probable Construction Cost (OPCC) was $1.3 million for the base bid and the proposal received exceeded the budgeted amount for this project. The Parks Development department has elected to reject all bids and will re-bid this project at a later date.
FINANCIAL SUMMARY:
• N/A
BOARD OR COMMISSION RECOMMENDATION:
• N/A